12824 N COMETA AVE 91340
Certificate Information: 12824 N COMETA AVE 91340
- Application / Permit
- 23014-20000-04406
- Plan Check / Job No.
- B23VN14769
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 16' X 22' SQ. FT. ADDITION TO THE (E) SINGLE FAMILY DWELLING. ALL WORK PER WFPP.
- Permit Issued
- Issued on 11/9/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/26/2023 | KAMYAR EMAMI |
| Corrections Issued | 10/26/2023 | KAMYAR EMAMI |
| Plan Check Approved | 11/8/2023 | LUISANGEL VALENZUELA |
| Issued | 11/9/2023 | APPLICANT |
| CofO in Progress | 7/5/2024 | ROBERT GOLD |
| CofO Issued | 7/8/2024 | RUBEN SALAS |
| Permit Finaled | 7/8/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/31/2023 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2023 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 11/1/2023 | EDGAR ALCARAZ |
| Miscellaneous | Cleared | 11/7/2023 | LEE GUILBEAUX |
| Watercourse | Cleared | 11/7/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/8/2024 | Approved | KEVIN BERBERYAN |
| Deputy Drilled-In Anchors | 3/13/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 3/26/2024 | Approved | KEVIN BERBERYAN |
| Wood Frame | 4/11/2024 | Partial Approval | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2024 | Approved | KEVIN BERBERYAN |
| Wood Frame | 4/17/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 4/29/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 4/29/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 4/29/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 5/7/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 5/7/2024 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 5/7/2024 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 5/7/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 5/7/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 5/7/2024 | Approved | KEVIN BERBERYAN |
| Insulation | 5/9/2024 | Corrections Issued | LEONARD ROSS II |
| Insulation | 5/13/2024 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 5/17/2024 | Approved | KEVIN BERBERYAN |
| Final | 6/11/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 6/11/2024 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 6/11/2024 | SGSOV Not Ready | KEVIN BERBERYAN |
| Smoke Detectors | 6/11/2024 | Approved | KEVIN BERBERYAN |
| Final | 6/14/2024 | OK to Issue CofO | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 6/14/2024 | SGSOV Approved | KEVIN BERBERYAN |