346 N LAS PALMAS AVE 90004
Certificate Information: 346 N LAS PALMAS AVE 90004
- Application / Permit
- 23014-20000-04383
- Plan Check / Job No.
- B23VN14709
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition of Patio Cover (11'-8" x 9'-4") and Interior Remodel on East side of exisitng 2-story Single Family Dwelling
- Permit Issued
- Issued on 2/12/2024
- Issuing Office
- Current Status
- CofO Issued on 4/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/26/2023 | VAHAN JIVALAGIAN |
| Corrections Issued | 10/28/2023 | VAHAN JIVALAGIAN |
| Quality Review Completed | 11/1/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 11/3/2023 | APPLICANT |
| Applicant returned to address corrections | 12/4/2023 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 1/25/2024 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 1/31/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 2/8/2024 | VAHAN JIVALAGIAN |
| Issued | 2/12/2024 | APPLICANT |
| CofO in Progress | 4/9/2026 | RONNIE MINDANAO |
| Permit Finaled | 4/12/2026 | DEROLD HAUFF |
| CofO Issued | 4/12/2026 | DEROLD HAUFF |
| Permit Finaled | 4/12/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/15/2023 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2023 | JUSTIN BICOL |
| HPOZ | Cleared | 2/2/2024 | SUKI GERSHENHORN |
Contact Information
| Contractor | Noble Construction Co; Lic. No.: 894239-B | 300 SYCAMORE GLEN PASADENA, CA 91105 |
| Engineer | Peck,, Christopher Mount; Lic. No.: C58162 | 25 SOUTH EL MOLINO AVE PASADENA, CA 911012023 |
| Engineer | Zweigler,, Robert Ingraham; Lic. No.: GE2120 | 1461 E. CHEVY CHASE DR. #200 GLENDALE, CA 91206 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/17/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Footing/Foundation/Slab | 6/25/2024 | Partial Approval | RONNIE MINDANAO |
| METHANE-Barrier | 6/25/2024 | Approved | RONNIE MINDANAO |
| METHANE-Subgrade | 6/25/2024 | Approved | RONNIE MINDANAO |
| Deputy Steel/Welding | 8/20/2024 | Conditional Approval | RONNIE MINDANAO |
| Footing/Foundation/Slab | 11/7/2024 | Conditional Approval | RONNIE MINDANAO |
| HVAC-Rough | 11/7/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Partial Approval | JOHN QUINTANILLA |
| Wood Frame | 11/12/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Insulation | 11/18/2024 | Partial Approval | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 1/17/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 1/17/2025 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2025 | Partial Approval | RONNIE MINDANAO |
| Green Building Rough | 1/17/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 1/17/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Rough | 1/17/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 1/17/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 1/23/2025 | Conditional Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Rough | 1/23/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 1/28/2025 | Conditional Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2025 | Partial Approval | RONNIE MINDANAO |
| Green Building Rough | 1/28/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 2/6/2025 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2025 | Approved | JOSE MACIAS |
| Green Building Rough | 2/6/2025 | Approved | JOSE MACIAS |
| Insulation | 2/6/2025 | Approved | JOSE MACIAS |
| Drywall Nailing | 2/11/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/8/2025 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 8/21/2025 | Corrections Issued | RONNIE MINDANAO |
| Final | 8/21/2025 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 8/21/2025 | Approved | RONNIE MINDANAO |
| Green Building Final | 8/21/2025 | Approved | RONNIE MINDANAO |
| HVAC-Final | 8/21/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| PLUMBING-Final | 8/21/2025 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 8/21/2025 | SGSOV Approved | RONNIE MINDANAO |
| Smoke Detectors | 8/21/2025 | Approved | RONNIE MINDANAO |
| Structural Steel Frame | 8/21/2025 | Conditional Approval | RONNIE MINDANAO |
| Final | 9/15/2025 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 9/15/2025 | Approved | JEFFREY MEAD |
| Structural Steel Frame | 9/15/2025 | Approved | JEFFREY MEAD |
| Final | 1/21/2026 | Corrections Issued | RONNIE MINDANAO |
| Final | 4/6/2026 | OK to Issue CofO | RONNIE MINDANAO |