23800 W WELBY WAY 91307
Certificate Information: 23800 W WELBY WAY 91307
- Application / Permit
- 23014-20000-04376
- Plan Check / Job No.
- B23VN14676
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel existing SFD with attached garage and addition of 20' 2" x 56' 5", with attached trellis, all work done per engineer. Remodel and addition of 20' 2" x 51' 1" to (E) SFD with attached garage to new dimensions of 72' 8" x 51'1", with attached trellis at the back. All work done per engineer.
- Permit Issued
- Issued on 1/31/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2023 | NAREG ATARIAN |
| Corrections Issued | 11/17/2023 | NAREG ATARIAN |
| Quality Review Completed | 11/21/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 12/22/2023 | NAREG ATARIAN |
| Building Plans Picked Up | 12/27/2023 | APPLICANT |
| Applicant returned to address corrections | 1/29/2024 | NAREG ATARIAN |
| Plan Check Approved | 1/31/2024 | NAREG ATARIAN |
| Issued | 1/31/2024 | APPLICANT |
| CofO in Progress | 10/3/2024 | GEVORK IPCHYAN |
| CofO Issued | 10/16/2024 | JOHN JANSON |
| Permit Finaled | 10/16/2024 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/19/2024 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 1/26/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 1/26/2024 | JOHN LIN |
Contact Information
| Contractor | Nes Construction Group Inc; Lic. No.: 996574-B | 8546 WOODLEY AVE NORTH HILLS, CA 91343 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/3/2024 | Partial Approval | TROY SANDERS |
| Underground Mechanical | 5/8/2024 | Corrections Issued | GEVORK IPCHYAN |
| Excavation/Setback/Form/Re-Bar | 5/10/2024 | Partial Approval | GEVORK IPCHYAN |
| Underground Mechanical | 5/10/2024 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 5/22/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Excavation/Setback/Form/Re-Bar | 5/22/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Excavation/Setback/Form/Re-Bar | 5/28/2024 | Approved | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 5/28/2024 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 6/4/2024 | Partial Approval | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2024 | Approved | GEVORK IPCHYAN |
| Green Building Rough | 6/4/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Wood Frame | 6/4/2024 | Partial Approval | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2024 | Approved | GEVORK IPCHYAN |
| Gas Test | 6/21/2024 | Partial Approval | GEVORK IPCHYAN |
| Green Building Rough | 6/21/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 6/21/2024 | Partial Approval | GEVORK IPCHYAN |
| Rough-Elec/Plmb/HVAC | 6/21/2024 | Approved | GEVORK IPCHYAN |
| Shower Pan | 6/21/2024 | Approved | GEVORK IPCHYAN |
| Underground Mechanical | 6/21/2024 | Approved | GEVORK IPCHYAN |
| Insulation | 6/26/2024 | Approved | GEVORK IPCHYAN |
| Service/Power Release | 6/26/2024 | Approved | GEVORK IPCHYAN |
| Drywall Nailing | 7/1/2024 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 7/1/2024 | Partial Approval | ALEXANDER HANDY |
| Interior/Exterior Lathing | 7/5/2024 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 8/30/2024 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 8/30/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Final | 8/30/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Final | 8/30/2024 | Approved | GEVORK IPCHYAN |
| HVAC-Final | 8/30/2024 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 8/30/2024 | Approved | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/30/2024 | SGSOV Approved | GEVORK IPCHYAN |
| Smoke Detectors | 8/30/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Final | 9/26/2024 | Partial Approval | GEVORK IPCHYAN |
| Smoke Detectors | 9/26/2024 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 10/2/2024 | Approved | GEVORK IPCHYAN |
| Final | 10/2/2024 | OK to Issue CofO | GEVORK IPCHYAN |