17103 W TRIBUNE ST 91344

Certificate Information: 17103 W TRIBUNE ST 91344

Application / Permit
23014-20000-04369
Plan Check / Job No.
B23VN14647
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION IRREGULAR SHAPED ( 33'-11" X 21'-6" ) TO EX. SFD FOR NEW DINING RM, BEDRM W/ BATH AND CLOSET ADDITION. INTERIOR REMODEL TO REPLACE EX 'DROPPED' BEAMS WITH 'FLUSHED' BEAMS OVER FAMILY/KITCHEN/LIVING RMS. REDUCE SIZE OF EX BEDRM FOR NEW HALLWAY AND REMODEL ONE BATHRM. WORK PER ENGINEER.
Permit Issued
Issued on 11/16/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/24/2023 APPLICANT
Assigned to Plan Check Engineer 10/27/2023 HAYATO TSUCHIYA
Corrections Issued 10/28/2023 HAYATO TSUCHIYA
Building Plans Picked Up 10/30/2023 APPLICANT
Plan Check Approved 11/16/2023 ROSENDO MEDINA
Issued 11/16/2023 APPLICANT
CofO in Progress 11/14/2024 STEVEN BACK
Permit Finaled 11/18/2024 JOHN JANSON
CofO Issued 11/18/2024 JOHN JANSON
Permit Finaled 11/18/2024 JOHN JANSON

Permit Application Clearance Information

Low Impact Development (LID) Cleared 11/6/2023 TOMMY YIN
Eng Process Fee Ord 176,300 Cleared 11/13/2023 COLIN LOREDO
Roof/Waste drainage to street Cleared 11/13/2023 COLIN LOREDO
Sewer availability Cleared 11/13/2023 COLIN LOREDO

Contact Information

Contractor Rela Remodeling Inc; Lic. No.: 1081199-B 12818 LA MAIDA STREET      VALLEY VILLAGE, CA 91607
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/9/2024 Approved JEFFREY PARD
Footing/Foundation/Slab 1/9/2024 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 1/16/2024 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 1/16/2024 Partial Approval JEFFREY PARD
Green Building Rough 1/16/2024 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 1/16/2024 Corrections Issued JEFFREY PARD
Deputy Wood Construction 1/17/2024 Approved JEFFREY PARD
BUILDING-Rough-Frame 1/19/2024 Partial Approval JEFFREY PARD
Green Building Rough 1/19/2024 Not Ready for Inspection JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 1/25/2024 Approved SEAN HAUPT
Deputy Wood Construction 2/1/2024 Approved JEFFREY PARD
BUILDING-Rough-Frame 2/12/2024 Not Ready for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 2/12/2024 Approved STEVEN BACK
Green Building Rough 2/12/2024 Not Ready for Inspection STEVEN BACK
Interior/Exterior Lathing 2/12/2024 Not Ready for Inspection STEVEN BACK
Rough-Elec/Plmb/HVAC 2/12/2024 Approved STEVEN BACK
Underground Mechanical 2/12/2024 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 2/15/2024 Approved STEVEN BACK
Green Building Rough 2/15/2024 Approved STEVEN BACK
Interior/Exterior Lathing 2/15/2024 Approved STEVEN BACK
Shower Pan 2/15/2024 Approved STEVEN BACK
Insulation 2/21/2024 Approved STEVEN BACK
Drywall Nailing 2/28/2024 Approved STEVEN BACK
Final 7/11/2024 Corrections Issued STEVEN BACK
Green Building Final 7/11/2024 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 7/11/2024 SGSOV Approved STEVEN BACK
Smoke Detectors 7/11/2024 Approved STEVEN BACK
Final 11/5/2024 Not Ready for Inspection STEVEN BACK
Final 11/14/2024 OK to Issue CofO STEVEN BACK