4170 N BAKMAN AVE 91602
Certificate Information: 4170 N BAKMAN AVE 91602
- Application / Permit
- 23014-20000-04363
- Plan Check / Job No.
- B23VN14617
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 17'-0" X 11'-0" ADDITION TO (E) SINGLE FAMILY DWELLING PER ENGINEERING.
- Permit Issued
- Issued on 11/9/2023
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 5/1/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 10/28/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 10/31/2023 | APPLICANT |
| Plan Check Approved | 11/9/2023 | GIOVANNY CHAVEZ |
| Issued | 11/9/2023 | APPLICANT |
| CofO in Progress | 5/1/2024 | CHRISTOPHER ROJAS |
| CofO in Progress | 1/13/2025 | CHRISTOPHER ROJAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/6/2023 | GABRIELLA TORRES |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2023 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barragan,, Pedro; Lic. No.: C90531 | 329 N HUBBARD AVE SAN FERNANDO, CA 91340 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/16/2023 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 11/21/2023 | Conditional Approval | JOHN COLEMAN |
| Deputy Drilled-In Anchors | 12/26/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2024 | Approved | KIRK SANDERS |
| Wood Frame | 1/4/2024 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 1/18/2024 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 1/18/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 1/18/2024 | Approved | KIRK SANDERS |
| HVAC-Rough | 1/18/2024 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 1/18/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 1/25/2024 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 1/25/2024 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 1/30/2024 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 2/6/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 4/18/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 4/18/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 4/18/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Final | 4/18/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 4/18/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 4/18/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 4/25/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 4/25/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 4/25/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Final | 5/1/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 5/1/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 5/1/2024 | SGSOV Approved | CHRISTOPHER ROJAS |