6017 N VARNA AVE 91401
Certificate Information: 6017 N VARNA AVE 91401
- Application / Permit
- 23014-20000-04359
- Plan Check / Job No.
- B23VN14604
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO AND CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d). WORK PER WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 09/22/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 6/13/2024
- Issuing Office
- Current Status
- CofO Issued on 12/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2023 | SARKIS HARABEDIAN |
| Corrections Issued | 10/30/2023 | SARKIS HARABEDIAN |
| Plan Check Approved | 6/12/2024 | ROSENDO MEDINA |
| Issued | 6/13/2024 | APPLICANT |
| CofO in Progress | 11/13/2025 | SCOTT SHUSTER |
| Permit Finaled | 12/19/2025 | DAVID JAMES |
| CofO Issued | 12/19/2025 | DAVID JAMES |
| Permit Finaled | 12/19/2025 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 1/13/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 1/13/2024 | EDGAR ALCARAZ |
| Construction near power lines | Cleared | 2/14/2024 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 6/11/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/25/2024 | Partial Inspection | SCOTT SHUSTER |
| Underground Mechanical | 4/1/2025 | Partial Approval | SCOTT SHUSTER |
| Pre-Inspection | 4/3/2025 | Partial Inspection | JOSE RUBIO |
| Deputy Drilled-In Anchors | 4/7/2025 | Approved | JOSE RUBIO |
| Footing/Foundation/Slab | 4/8/2025 | Approved | JOSE RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2025 | Approved | JOSE RUBIO |
| Shower Pan | 5/5/2025 | Partial Inspection | JOSE RUBIO |
| Shower Pan | 5/9/2025 | Approved | JOSE RUBIO |
| Pre-Inspection | 5/20/2025 | Partial Inspection | JOSE RUBIO |
| Interior/Exterior Lathing | 5/27/2025 | Corrections Issued | SCOTT SHUSTER |
| Rough-Elec/Plmb/HVAC | 5/27/2025 | Corrections Issued | SCOTT SHUSTER |
| Sewer | 5/27/2025 | Approved | SCOTT SHUSTER |
| ELECTRICAL-Rough | 5/30/2025 | Partial Inspection | SCOTT SHUSTER |
| Interior/Exterior Lathing | 5/30/2025 | Partial Approval | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 6/4/2025 | Approved | JOSE RUBIO |
| ELECTRICAL-Rough | 6/4/2025 | Approved | JOSE RUBIO |
| Green Building Rough | 6/4/2025 | Approved | JOSE RUBIO |
| HVAC-Rough | 6/4/2025 | Approved | JOSE RUBIO |
| PLUMBING-Rough | 6/4/2025 | Approved | JOSE RUBIO |
| Underground Mechanical | 6/4/2025 | Approved | JOSE RUBIO |
| Interior/Exterior Lathing | 6/10/2025 | Approved | JOSE RUBIO |
| Insulation | 6/12/2025 | Approved | JOSE RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2025 | Approved | JOSE RUBIO |
| Drywall Nailing | 6/20/2025 | Approved | JOSE RUBIO |
| Pre-Inspection | 8/13/2025 | Partial Inspection | JOSE RUBIO |
| Final | 10/17/2025 | Partial Inspection | JOSE RUBIO |
| Green Building Final | 10/17/2025 | Approved | JOSE RUBIO |
| SGSOV-Seismic Gas S/O Valve | 10/17/2025 | SGSOV Approved | JOSE RUBIO |
| Smoke Detectors | 10/17/2025 | Partial Inspection | JOSE RUBIO |
| Grounding or Bonding | 10/24/2025 | Approved | JOSE RUBIO |
| Smoke Detectors | 10/24/2025 | Partial Inspection | JOSE RUBIO |
| Final | 11/4/2025 | Conditional Approval | THOMAS WOODS |
| Smoke Detectors | 11/4/2025 | Approved | THOMAS WOODS |
| Final | 11/12/2025 | OK to Issue CofO | SCOTT SHUSTER |