14509 1/2 W GREENLEAF ST 91403

Certificate Information: 14509 1/2 W GREENLEAF ST 91403

Application / Permit
23014-20000-04356
Plan Check / Job No.
B23VN14597
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New one story 26' x 41' ADU per LAMC 12.22 A.33 (c)-(d). All work done per engineer.
Permit Issued
Issued on 10/25/2024
Issuing Office
Valley
Current Status
CofO Issued on 7/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2023 APPLICANT
Assigned to Plan Check Engineer 10/26/2023 NAREG ATARIAN
Corrections Issued 10/28/2023 NAREG ATARIAN
Quality Review Completed 10/31/2023 OMID HEDAYAT
Building Plans Picked Up 11/1/2023 APPLICANT
Plan Check Approved 10/9/2024 NAREG ATARIAN
Issued 10/25/2024 APPLICANT
CofO in Progress 6/30/2025 JUAN VALENZUELA
CofO in Progress 7/1/2025 DAVID MATSON
Permit Finaled 7/3/2025 RUBEN SALAS
CofO Issued 7/3/2025 RUBEN SALAS
Permit Finaled 7/3/2025 RUBEN SALAS

Permit Application Clearance Information

Senate Bill 9 Cleared 11/16/2023 NELSON RODRIGUEZ
Grading Pre-Inspection Cleared 4/23/2024 CHARLES POWELL
Address approval Cleared 4/25/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 4/25/2024 EDGAR ALCARAZ
Sewer availability Cleared 4/25/2024 EDGAR ALCARAZ
Hydrant and Access approval Cleared 5/18/2024 JOHN CONNEALLY
Construction within easement Cleared 6/14/2024 RIDWAN HARDY
Miscellaneous Cleared 8/20/2024 MAX LODER
Low Impact Development (LID) Cleared 10/3/2024 MITESH PATEL
Roof/Waste drainage to street Cleared 10/8/2024 BRYAN GODINEZ
GPI Written Notices Cleared 10/9/2024 ROBERT PINA

Contact Information

Contractor Owner-Builder       ,
Engineer Foroughikia,, Babak; Lic. No.: C94091 21930 MARYLEE ST APT 87      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/16/2024 Approved MISAEL ESPARZA
Underground Mechanical 12/24/2024 Partial Approval RYAN SALAZAR
PLUMBING-Rough 12/30/2024 Partial Approval MISAEL ESPARZA
Sewer 12/30/2024 Approved MISAEL ESPARZA
Footing/Foundation/Slab 1/3/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 1/17/2025 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/22/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 1/28/2025 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 2/3/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 2/12/2025 Approved MISAEL ESPARZA
Insulation 2/18/2025 Corrections Issued MISAEL ESPARZA
Shower Pan 2/18/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 2/27/2025 Corrections Issued MISAEL ESPARZA
Green Building Rough 2/27/2025 Approved MISAEL ESPARZA
HVAC-Rough 2/27/2025 Corrections Issued MISAEL ESPARZA
Insulation 2/27/2025 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 2/27/2025 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 3/3/2025 Conditional Approval MISAEL ESPARZA
HVAC-Rough 3/3/2025 Approved MISAEL ESPARZA
Insulation 3/3/2025 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 3/3/2025 Partial Inspection MISAEL ESPARZA
Drywall Nailing 3/6/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 3/6/2025 Approved MISAEL ESPARZA
ELECTRICAL-Final 4/17/2025 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 4/17/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 4/25/2025 Corrections Issued JAVIER RAMOS JR
PLUMBING-Final 4/25/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 5/15/2025 Conditional Approval MISAEL ESPARZA
ELECTRICAL-Final 5/15/2025 Approved MISAEL ESPARZA
Final 5/15/2025 Corrections Issued MISAEL ESPARZA
Green Building Final 5/15/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 5/15/2025 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 5/15/2025 SGSOV Not Required MISAEL ESPARZA
Service/Power Release 5/15/2025 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 5/15/2025 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 5/15/2025 Partial Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 5/20/2025 Approved MISAEL ESPARZA
Final 5/20/2025 Corrections Issued MISAEL ESPARZA
Green Building Final 5/20/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 5/20/2025 Not Ready for Inspection MISAEL ESPARZA
Service/Power Release 5/20/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 6/24/2025 Approved MISAEL ESPARZA
Final 6/24/2025 OK to Issue CofO MISAEL ESPARZA
Green Building Final 6/24/2025 Approved MISAEL ESPARZA
Service/Power Release 6/24/2025 Approved MISAEL ESPARZA
Final 6/30/2025 OK to Issue CofO DAVID MATSON