11702-11704 N MONOGRAM AVE 91344
Certificate Information: 11702-11704 N MONOGRAM AVE 91344
- Application / Permit
- 23014-20000-04353
- Plan Check / Job No.
- B23VN14582
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 23'-2" X 20'-10" ON SECOND FLOOR AND CONVERT EXISTING ATTACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e); ADD 10'-10" X 10' TO EXISTING DWELLING TO ADD CLOSET AND AND ENLARGE BATHROOM IN EXISTING BEDROOM
- Permit Issued
- Issued on 10/31/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2023 | SELLA BENYAMIN |
| Corrections Issued | 11/9/2023 | SELLA BENYAMIN |
| Quality Review Completed | 11/14/2023 | STEVEN KIM |
| Building Plans Picked Up | 11/15/2023 | APPLICANT |
| Plan Check Approved | 10/31/2024 | SELLA BENYAMIN |
| Issued | 10/31/2024 | APPLICANT |
| CofO in Progress | 7/3/2025 | RAUL OLAGI |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
| CofO Issued | 7/8/2025 | RUBEN SALAS |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/4/2024 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 1/4/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 1/5/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Hi - Crest Construction Inc; Lic. No.: 930717-B | 710 E SAN JOSE AVE # C BURBANK, CA 91501 |
| Engineer | Karapetian,, Arbi; Lic. No.: C79953 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/16/2024 | Partial Approval | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 12/17/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 12/18/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/20/2025 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 2/20/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Rough | 2/20/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 2/20/2025 | Partial Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 2/20/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 2/24/2025 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 2/24/2025 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 3/3/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/3/2025 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 3/3/2025 | Corrections Issued | JACK KARGODORIAN |
| Shower Pan | 3/5/2025 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 3/12/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 3/12/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 5/8/2025 | Approved | RAUL OLAGI |
| Final | 5/8/2025 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 5/8/2025 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 5/8/2025 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 5/8/2025 | Approved | RAUL OLAGI |
| Final | 7/2/2025 | OK to Issue CofO | RAUL OLAGI |
| Service/Power Release | 7/2/2025 | Approved | RAUL OLAGI |