830 W 82ND ST 90044

Certificate Information: 830 W 82ND ST 90044

Application / Permit
23014-20000-04326
Plan Check / Job No.
B23VN14491
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k).
Permit Issued
Issued on 10/14/2025
Issuing Office
Valley
Current Status
Issued on 10/14/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/20/2023 APPLICANT
Assigned to Plan Check Engineer 10/25/2023 ARTIN ZARUKIAN
Corrections Issued 10/30/2023 ARTIN ZARUKIAN
Building Plans Picked Up 11/9/2023 APPLICANT
Plan Check Approved 10/14/2025 ROSENDO MEDINA
Issued 10/14/2025 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 5/20/2024 RIDWAN HARDY
Address approval Cleared 8/26/2025 DERRICK MAGEE
Roof/Waste drainage to street Cleared 8/26/2025 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 8/28/2025 DERRICK MAGEE
Sewer availability Cleared 8/28/2025 DERRICK MAGEE
ZI Cleared 8/29/2025 FIPE LEILUA

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/13/2026 Corrections Issued JOHN QUINTANILLA
Underground Mechanical 2/13/2026 Approved JOHN QUINTANILLA
Underground Mechanical 3/25/2026 Approved JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 4/1/2026 Approved JOHN QUINTANILLA
Underground Mechanical 4/1/2026 Approved JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 4/3/2026 Not Ready for Inspection JOHN QUINTANILLA
Footing/Foundation/Slab 4/3/2026 Not Ready for Inspection JOHN QUINTANILLA
Footing/Foundation/Slab 4/7/2026 Approved JOHN QUINTANILLA
Footing/Foundation/Slab 4/9/2026 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 4/23/2026 Not Ready for Inspection JOHN QUINTANILLA
Green Building Rough 4/23/2026 Not Ready for Inspection JOHN QUINTANILLA
Wood Frame 4/23/2026 Not Ready for Inspection JOHN QUINTANILLA
Wood Frame 4/24/2026 Not Ready for Inspection JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 4/28/2026 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 5/5/2026 Approved JOHN QUINTANILLA
HVAC-Rough 5/5/2026 Corrections Issued JOHN QUINTANILLA
PLUMBING-Rough 5/5/2026 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 5/6/2026 Approved JOHN QUINTANILLA
Shower Pan 5/6/2026 Approved JOHN QUINTANILLA
HVAC-Rough 5/12/2026 Approved JOHN QUINTANILLA
Wood Frame 5/13/2026 Approved JOHN QUINTANILLA
Insulation 5/19/2026 Approved JOHN QUINTANILLA
Drywall Nailing 5/22/2026 Approved BRIAN SULLIVAN
Green Building Rough 5/22/2026 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 5/22/2026 Partial Approval BRIAN SULLIVAN