11539-11541 N RUFFNER AVE 91344

Certificate Information: 11539-11541 N RUFFNER AVE 91344

Application / Permit
23014-20000-04314
Plan Check / Job No.
B23VN14465
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* CONVERT (39 S.F) PORTION OF (E) ATT. GARAGE TO A NEW LAUNDRY ROOM FOR THE (E) SFD AND (447 S.F) PORTION OF (E) ATT. GARAGE TO A NEW ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). ALL WORK PER WFPP.
Permit Issued
Issued on 11/9/2023
Issuing Office
Current Status
CofO Issued on 4/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2023 APPLICANT
Assigned to Plan Check Engineer 10/24/2023 SARKIS HARABEDIAN
Corrections Issued 10/25/2023 SARKIS HARABEDIAN
Plan Check Approved 11/9/2023 SELLA BENYAMIN
Issued 11/9/2023 APPLICANT
CofO in Progress 3/10/2025 JAVIER RAMOS JR
Permit Finaled 4/10/2025 RUBEN SALAS
Permit Finaled 4/10/2025 RUBEN SALAS
CofO Issued 4/10/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/27/2023 BRYAN GODINEZ
Sewer availability Cleared 10/27/2023 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 10/30/2023 BRYAN GODINEZ
Grading Pre-Inspection Cleared 11/2/2023 JONATHAN HOM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/1/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 4/11/2024 Partial Approval JAVIER RAMOS JR
Sewer 4/11/2024 Approved JAVIER RAMOS JR
Underground Mechanical 4/11/2024 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 5/6/2024 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 5/6/2024 Corrections Issued JAVIER RAMOS JR
Green Building Rough 5/6/2024 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 5/28/2024 Approved JAVIER RAMOS JR
HVAC-Rough 5/28/2024 Partial Inspection JAVIER RAMOS JR
PLUMBING-Rough 5/28/2024 Approved JAVIER RAMOS JR
Insulation 6/12/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 7/1/2024 Approved JAVIER RAMOS JR
Drywall Nailing 7/1/2024 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 7/1/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 7/1/2024 Approved JAVIER RAMOS JR
Green Building Rough 7/1/2024 Approved JAVIER RAMOS JR
HVAC-Rough 7/1/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 7/1/2024 Approved JAVIER RAMOS JR
Drywall Nailing 7/8/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 1/21/2025 Partial Inspection JAVIER RAMOS JR
Final 1/21/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 1/21/2025 Approved JAVIER RAMOS JR
HVAC-Final 1/21/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 1/21/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 1/21/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 2/18/2025 Partial Inspection JAVIER RAMOS JR
Final 2/18/2025 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Final 2/18/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 2/18/2025 SGSOV Approved JAVIER RAMOS JR
ELECTRICAL-Final 3/7/2025 Approved JAVIER RAMOS JR
Final 3/7/2025 OK to Issue CofO JAVIER RAMOS JR