16049 W CHASE AVE 91343
Certificate Information: 16049 W CHASE AVE 91343
- Application / Permit
- 23014-20000-04303
- Plan Check / Job No.
- B23VN14405
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** New Dettached Accessory Dwelling Unit per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 6/25/2024
- Issuing Office
- Current Status
- CofO Issued on 9/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2023 | ALFREDO JARA |
| Corrections Issued | 10/24/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 3/15/2024 | ALFREDO JARA |
| Applicant returned to address corrections | 3/28/2024 | EDWIN ESPIN |
| Applicant returned to address corrections | 4/4/2024 | EDWIN ESPIN |
| Applicant returned to address corrections | 4/6/2024 | EDWIN ESPIN |
| Plan Check Approved | 5/6/2024 | EDWIN ESPIN |
| Issued | 6/25/2024 | APPLICANT |
| CofO in Progress | 9/22/2025 | GAREN HAYRAPETYAN |
| CofO Issued | 9/23/2025 | RUBEN SALAS |
| Permit Finaled | 9/23/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/4/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2023 | COLIN LOREDO |
| ZA Case | Cleared | 11/21/2023 | ALEX VELA |
| Construction near power lines | Cleared | 2/10/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 2/28/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 3/2/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 3/4/2024 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/20/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 11/20/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 11/25/2024 | Approved | LOUIS ESCOTO |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2024 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 1/10/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Rough | 1/10/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 1/10/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 3/7/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 3/7/2025 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 3/7/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Rough | 3/7/2025 | Approved | SALVADOR MARTINEZ |
| Verify Sprinkler Sign Off | 3/7/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 3/17/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 3/17/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Rough | 4/1/2025 | Approved | RAUL OLAGI |
| Insulation | 4/1/2025 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 4/1/2025 | Partial Approval | RAUL OLAGI |
| Insulation | 4/4/2025 | Approved | RAUL OLAGI |
| Insulation | 4/14/2025 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 4/30/2025 | Approved | SALVADOR MARTINEZ |
| Shower Pan | 6/6/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 6/16/2025 | Approved | NICHOLAS TROWBRIDGE |
| Shower Pan | 6/16/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 7/15/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 7/15/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 7/15/2025 | Approved | SALVADOR MARTINEZ |
| Green Building Final | 7/15/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Final | 7/15/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 7/15/2025 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 7/15/2025 | SGSOV Not Required | SALVADOR MARTINEZ |
| Service/Power Release | 7/15/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 7/15/2025 | Approved | SALVADOR MARTINEZ |
| Final | 9/12/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Service/Power Release | 9/12/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Pre-Inspection | 9/16/2025 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Final | 9/17/2025 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Final | 9/17/2025 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Final | 9/17/2025 | Corrections Issued | JAVIER RAMOS JR |
| Final | 9/22/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Service/Power Release | 9/22/2025 | Approved | GAREN HAYRAPETYAN |