15024 W VOSE ST 91405
Certificate Information: 15024 W VOSE ST 91405
- Application / Permit
- 23014-20000-04290
- Plan Check / Job No.
- B23VN14369
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 13'-0" X 29'- 4" ADDITION TO & CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 12/18/2023
- Issuing Office
- Current Status
- CofO Issued on 7/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 10/23/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 10/25/2023 | APPLICANT |
| Applicant returned to address corrections | 12/13/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 12/18/2023 | OMAR GARNICA |
| Issued | 12/18/2023 | APPLICANT |
| CofO in Progress | 6/28/2024 | RYAN SALAZAR |
| CofO in Progress | 7/1/2024 | RYAN SALAZAR |
| Permit Finaled | 7/10/2024 | RUBEN SALAS |
| CofO Issued | 7/10/2024 | RUBEN SALAS |
| Permit Finaled | 7/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/26/2023 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 10/26/2023 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/27/2023 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 11/27/2023 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/7/2024 | Partial Approval | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 2/13/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 2/15/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 2/16/2024 | Approved | CRAIG DAVIS |
| ELECTRICAL-Rough | 3/21/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 3/21/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 3/21/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 4/11/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 4/11/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 4/11/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Footing/Foundation/Slab | 4/11/2024 | Approved | RYAN SALAZAR |
| Green Building Final | 4/11/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Insulation | 4/11/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 4/11/2024 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 4/11/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 4/11/2024 | SGSOV Not Ready | RYAN SALAZAR |
| Drywall Nailing | 4/17/2024 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 4/17/2024 | Approved | JOHN COLEMAN |
| Shower Pan | 4/17/2024 | Approved | JOHN COLEMAN |
| Underground Mechanical | 5/14/2024 | Approved | RYAN SALAZAR |
| Final | 6/4/2024 | Corrections Issued | JOHN COLEMAN |
| Green Building Final | 6/4/2024 | Corrections Issued | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 6/4/2024 | SGSOV Not Ready | JOHN COLEMAN |
| Smoke Detectors | 6/4/2024 | Approved | JOHN COLEMAN |
| Final | 6/12/2024 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 6/12/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 6/12/2024 | SGSOV Approved | RYAN SALAZAR |
| Final | 6/25/2024 | OK to Issue CofO | RYAN SALAZAR |
| Final | 6/27/2024 | OK to Issue CofO | RYAN SALAZAR |
| Service/Power Release | 6/27/2024 | Approved | RYAN SALAZAR |