12218 W OTSEGO ST 91607
Certificate Information: 12218 W OTSEGO ST 91607
- Application / Permit
- 23014-20000-04270
- Plan Check / Job No.
- B23VN14316
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 18'-11" x 6'-0" ADDITION TO THE (E) SINGLE FAMILY DWELLING FOR A NEW CLOSET TO THE MASTER BEDROOM AND REFRAME PORTION OF (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 12/11/2023
- Issuing Office
- Current Status
- CofO Issued on 6/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2023 | GIOVANNY CHAVEZ |
| Corrections Issued | 10/25/2023 | GIOVANNY CHAVEZ |
| Plan Check Approved | 12/10/2023 | SARKIS HARABEDIAN |
| Issued | 12/11/2023 | APPLICANT |
| CofO in Progress | 5/30/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 6/22/2024 | RUBEN SALAS |
| CofO Issued | 6/22/2024 | RUBEN SALAS |
| Permit Finaled | 6/22/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/30/2023 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2023 | CARLOS RAMIREZ |
| Specific Plan | Cleared | 12/5/2023 | JOANNA MARROQUIN |
Contact Information
| Contractor | All Shapes Construction & Design Inc; Lic. No.: 1098943-B | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/17/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 1/25/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Corrections Issued | JOSE AVILA |
| Deputy Drilled-In Anchors | 3/28/2024 | Conditional Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 3/29/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 4/2/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Deputy Wood Construction | 4/2/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 4/2/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 4/2/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 4/4/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 4/4/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 4/4/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 4/8/2024 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/2/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 5/2/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 5/2/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 5/2/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 5/2/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 5/2/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 5/2/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 5/2/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 5/24/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 5/24/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 5/24/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 5/29/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 5/29/2024 | Approved | OGANES TARAKHCHYAN |