8948-8950 N BALBOA BLVD 91325
Certificate Information: 8948-8950 N BALBOA BLVD 91325
- Application / Permit
- 23014-20000-04268
- Plan Check / Job No.
- B23VN14310
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE WITH 9'-6"X20'-0"ADDITION INTO A (N) IRREGULAR SHAPED ACCESSORY DWELLING UNIT WITH 3'-0"X8'-0" FRONT PORCH ADDITION TO COMPLY WITH LAMC 12.22 A.33(c) AND (e) AND CONVERT AND ENCLOSE (E) BREEZEWAY INTO A (N) ATTACHED STORAGE (EXTERIOR ACCESS ONLY) PER WFPP
- Permit Issued
- Issued on 12/12/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2023 | SERGIO MUNIZ |
| Corrections Issued | 10/21/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 10/30/2023 | APPLICANT |
| Applicant returned to address corrections | 11/6/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 11/21/2023 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 11/27/2023 | JESSE ARELLANO |
| Applicant returned to address corrections | 12/7/2023 | JESSE ARELLANO |
| Issued | 12/12/2023 | APPLICANT |
| CofO in Progress | 7/16/2025 | SALVADOR MARTINEZ |
| Permit Finaled | 9/10/2025 | RUBEN SALAS |
| CofO Issued | 9/10/2025 | RUBEN SALAS |
| Permit Finaled | 9/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/30/2023 | NIKKI ZULUETA |
| Roof/Waste drainage to street | Cleared | 10/30/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 10/30/2023 | NIKKI ZULUETA |
| Tract Map conditions | Cleared | 10/31/2023 | YINGSHI HUANG |
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2023 | NIKKI ZULUETA |
| Watercourse | Cleared | 11/7/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: C56881 | 8325 FOOTHILL BLVD. STE A SUNLAND, CA 91040 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/19/2024 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 1/29/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 3/4/2024 | Approved | RAUL OLAGI |
| Sewer | 3/4/2024 | Approved | RAUL OLAGI |
| Wood Frame | 3/7/2024 | Not Ready for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2024 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 3/22/2024 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2024 | Partial Approval | RAUL OLAGI |
| Shower Pan | 3/22/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 4/4/2024 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/9/2024 | Approved | RAUL OLAGI |
| Green Building Rough | 4/9/2024 | Approved | RAUL OLAGI |
| HVAC-Rough | 4/9/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 4/9/2024 | Partial Approval | RAUL OLAGI |
| Insulation | 4/16/2024 | Corrections Issued | RAUL OLAGI |
| Drywall Nailing | 4/22/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Drywall Nailing | 4/26/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Drywall Nailing | 5/1/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 5/1/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Drywall Nailing | 5/3/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 5/3/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Drywall Nailing | 5/14/2024 | Approved | RAUL OLAGI |
| Insulation | 5/14/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/14/2024 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 8/15/2024 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 11/1/2024 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 11/4/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 3/17/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 3/17/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Final | 3/17/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 3/17/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 3/17/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 4/1/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Green Building Final | 4/1/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 4/8/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 4/25/2025 | OK to Issue CofO | SALVADOR MARTINEZ |
| Service/Power Release | 4/25/2025 | Approved | SALVADOR MARTINEZ |