9001 N NOBLE AVE 91343

Certificate Information: 9001 N NOBLE AVE 91343

Application / Permit
23014-20000-04247
Plan Check / Job No.
B23VN14227
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ENTIRE SFD EXCEPT 4LF OF WALL & FOOTING & ADD 1-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 1/18/2024
Issuing Office
Current Status
CofO Issued on 1/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/16/2023 APPLICANT
Assigned to Plan Check Engineer 10/19/2023 NILOOFAR MEHRAIN
Corrections Issued 10/21/2023 NILOOFAR MEHRAIN
Quality Review Completed 10/25/2023 STEVEN KIM
Applicant returned to address corrections 1/12/2024 NILOOFAR MEHRAIN
Plan Check Approved 1/18/2024 NILOOFAR MEHRAIN
Plan Check Approved 1/18/2024 NILOOFAR MEHRAIN
Issued 1/18/2024 APPLICANT
CofO in Progress 1/2/2025 VINCENT HANLEY
Permit Finaled 1/8/2025 RUBEN SALAS
CofO Issued 1/8/2025 RUBEN SALAS
Permit Finaled 1/8/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/27/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/30/2023 COLIN LOREDO
Sewer availability Cleared 10/30/2023 COLIN LOREDO
Hydrant and Access approval Cleared 11/3/2023 LAVEON RIDER
Low Impact Development (LID) Cleared 1/10/2024 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 1/11/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/23/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/11/2024 Partial Approval CHRISTOPHER ROJAS
Underground Mechanical 3/11/2024 Approved CHRISTOPHER ROJAS
Insulation 3/13/2024 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 3/13/2024 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 3/18/2024 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/11/2024 Partial Approval KIRK SANDERS
HVAC-Rough 4/22/2024 Corrections Issued KIRK SANDERS
PLUMBING-Rough 4/22/2024 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 4/26/2024 Partial Approval KIRK SANDERS
HVAC-Rough 4/26/2024 Approved KIRK SANDERS
PLUMBING-Rough 4/26/2024 Approved KIRK SANDERS
Shower Pan 4/26/2024 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/1/2024 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 5/1/2024 Approved KIRK SANDERS
Interior/Exterior Lathing 5/6/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 5/13/2024 Approved VINCENT HANLEY
ELECTRICAL-Rough 5/13/2024 Approved VINCENT HANLEY
Insulation 5/20/2024 Approved VINCENT HANLEY
Drywall Nailing 5/28/2024 Approved MATTHEW NELSON
ELECTRICAL-Final 7/29/2024 Approved VINCENT HANLEY
Gas Test 7/29/2024 Approved VINCENT HANLEY
PLUMBING-Final 7/29/2024 Approved VINCENT HANLEY
Service/Power Release 7/29/2024 Approved VINCENT HANLEY
ELECTRICAL-Final 8/30/2024 Approved VINCENT HANLEY
HVAC-Final 8/30/2024 Approved VINCENT HANLEY
Final 10/25/2024 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 10/25/2024 SGSOV Approved VINCENT HANLEY
Smoke Detectors 10/25/2024 Approved VINCENT HANLEY
Final 1/2/2025 OK to Issue CofO VINCENT HANLEY