9003 N NOBLE AVE 91343
Certificate Information: 9003 N NOBLE AVE 91343
- Application / Permit
- 23014-20000-04230
- Plan Check / Job No.
- B23VN14158
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE WITH ADDITION INTO A (N) IRREGULAR SHAPED 43'-0" x 29'-8" ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) AND (d) WITH ATTACHED FRONT PORCH PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
- Permit Issued
- Issued on 1/18/2024
- Issuing Office
- Current Status
- CofO Issued on 1/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2023 | ALFRED RAMIREZ |
| Corrections Issued | 10/18/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 1/16/2024 | ALFRED RAMIREZ |
| Plan Check Approved | 1/18/2024 | ALFRED RAMIREZ |
| Issued | 1/18/2024 | APPLICANT |
| CofO in Progress | 1/2/2025 | VINCENT HANLEY |
| Permit Finaled | 1/9/2025 | RUBEN SALAS |
| CofO Issued | 1/9/2025 | RUBEN SALAS |
| Permit Finaled | 1/9/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/27/2023 | LAVEON RIDER |
| Address approval | Cleared | 11/9/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/9/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 1/10/2024 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/11/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/23/2024 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 2/23/2024 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2024 | Partial Approval | JOHN COLEMAN |
| BUILDING-Rough-Frame | 4/12/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 4/12/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2024 | Partial Approval | KIRK SANDERS |
| HVAC-Rough | 4/12/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 4/12/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 4/18/2024 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 4/18/2024 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 4/18/2024 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 4/18/2024 | Approved | KIRK SANDERS |
| Shower Pan | 4/22/2024 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 4/26/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/6/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 5/6/2024 | Approved | KIRK SANDERS |
| Verify Sprinkler Sign Off | 5/6/2024 | Approved | KIRK SANDERS |
| Insulation | 5/13/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 5/28/2024 | Approved | MATTHEW NELSON |
| Underground Mechanical | 7/15/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 7/29/2024 | Approved | VINCENT HANLEY |
| Gas Test | 7/29/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 7/29/2024 | Approved | VINCENT HANLEY |
| Service/Power Release | 7/29/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 8/30/2024 | Approved | VINCENT HANLEY |
| HVAC-Final | 8/30/2024 | Approved | VINCENT HANLEY |
| Final | 10/28/2024 | No Access for Inspection | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 10/28/2024 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 10/28/2024 | No Access for Inspection | VINCENT HANLEY |
| Final | 1/2/2025 | OK to Issue CofO | VINCENT HANLEY |
| Smoke Detectors | 1/2/2025 | Approved | VINCENT HANLEY |