5320 N IRVINE AVE 91601

Certificate Information: 5320 N IRVINE AVE 91601

Application / Permit
23014-20000-04218
Plan Check / Job No.
B23VN14135
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan ADDITION TO EXISTING SINGLE FAMILY DWELLING PER ENGINEER
Permit Issued
Issued on 1/5/2024
Issuing Office
Current Status
CofO Issued on 1/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/17/2023 APPLICANT
Assigned to Plan Check Engineer 10/19/2023 MINA HABILI
Corrections Issued 10/20/2023 MINA HABILI
Applicant returned to address corrections 12/27/2023 KHUONG TRUONG
Plan Check Approved 1/3/2024 WEIJIAN HUANG
Issued 1/5/2024 APPLICANT
CofO in Progress 8/12/2024 CHRISTOPHER ROJAS
CofO in Progress 8/20/2024 JUAN VALENZUELA
CofO in Progress 8/21/2024 CHRISTOPHER ROJAS
CofO in Progress 12/30/2024 CHRISTOPHER ROJAS
Permit Finaled 1/16/2025 RUBEN SALAS
CofO Issued 1/16/2025 RUBEN SALAS
Permit Finaled 1/16/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/21/2023 EDGAR ALCARAZ
Miscellaneous Cleared 11/30/2023 NELSON RODRIGUEZ
Specific Plan Cleared 12/6/2023 CHRISTIAN PEARSON
ZI Cleared 12/6/2023 CHRISTIAN PEARSON
ZI Cleared 12/6/2023 CHRISTIAN PEARSON
Low Impact Development (LID) Cleared 12/21/2023 TRISH PARAS
Roof/Waste drainage to street Cleared 12/22/2023 EDGAR ALCARAZ

Contact Information

Architect Rodriguez,, Hector Manuel; Lic. No.: NA39395       ,
Contractor Maven Associates Inc The; Lic. No.: 1085625-B       ,
Engineer Baich,, Brendon Chad; Lic. No.: C83347 PO BOX 8840      POMONA, CA 91701

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/9/2024 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/15/2024 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Corrections Issued KIRK SANDERS
Insulation 2/16/2024 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/20/2024 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 2/28/2024 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/4/2024 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 3/12/2024 Partial Approval JOHN COLEMAN
BUILDING-Rough-Frame 3/26/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 3/26/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 3/26/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 3/26/2024 Approved CHRISTOPHER ROJAS
MERV13>=Rough 3/26/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 3/26/2024 Approved CHRISTOPHER ROJAS
Wood Frame 3/26/2024 Approved CHRISTOPHER ROJAS
Insulation 4/9/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 4/12/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 4/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Shower Pan 4/12/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 4/16/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 6/14/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Final 6/14/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 6/14/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Final 6/14/2024 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Final 6/14/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 6/14/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 6/14/2024 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 6/14/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 6/24/2024 Approved ROBERT GOLD
Final 6/24/2024 Corrections Issued ROBERT GOLD
Green Building Final 6/24/2024 Approved ROBERT GOLD
HVAC-Final 6/24/2024 Approved ROBERT GOLD
MERV13>=Final 6/24/2024 Approved ROBERT GOLD
PLUMBING-Final 6/24/2024 Approved ROBERT GOLD
Final 8/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Final 8/21/2024 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 10/31/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Final 12/30/2024 OK to Issue CofO CHRISTOPHER ROJAS