10447 N WOODLEY AVE 91344

Certificate Information: 10447 N WOODLEY AVE 91344

Application / Permit
23014-20000-04211
Plan Check / Job No.
B23VN14080
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Convert existing garage 400 SF into ADU and add 225 SF to the proposed ADU. PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 1/5/2024
Issuing Office
Current Status
CofO Issued on 7/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2023 APPLICANT
Assigned to Plan Check Engineer 10/17/2023 ALFREDO JARA
Corrections Issued 10/17/2023 ALFREDO JARA
Applicant returned to address corrections 11/17/2023 ALFREDO JARA
Plan Check Approved 1/4/2024 JASON JANGADA
Issued 1/5/2024 APPLICANT
CofO in Progress 6/25/2025 NICHOLAS TROWBRIDGE
Permit Finaled 7/8/2025 RUBEN SALAS
CofO Issued 7/8/2025 RUBEN SALAS
Permit Finaled 7/8/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/15/2023 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 11/15/2023 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 11/15/2023 CARLOS RAMIREZ
Sewer availability Cleared 11/16/2023 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: NA4808       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/29/2024 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/17/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 5/8/2024 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 5/8/2024 Corrections Issued JAVIER RAMOS JR
Green Building Rough 5/8/2024 Not Ready for Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 5/8/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 5/8/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 5/28/2024 Corrections Issued KEVIN BERBERYAN
HVAC-Rough 5/28/2024 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 6/20/2024 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 6/20/2024 Approved JAVIER RAMOS JR
Green Building Rough 6/20/2024 Approved JAVIER RAMOS JR
HVAC-Rough 6/20/2024 Corrections Issued JAVIER RAMOS JR
Insulation 6/25/2024 Approved JAVIER RAMOS JR
Drywall Nailing 7/18/2024 Approved JAVIER RAMOS JR
Shower Pan 7/18/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 8/21/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 9/25/2024 Approved JAVIER RAMOS JR
Final 9/25/2024 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 9/25/2024 Approved JAVIER RAMOS JR
Green Building Final 9/25/2024 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 9/25/2024 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 9/25/2024 Not Ready for Inspection JAVIER RAMOS JR
Final 11/1/2024 No Access for Inspection JAVIER RAMOS JR
ELECTRICAL-Final 6/20/2025 Corrections Issued NICHOLAS TROWBRIDGE
Final 6/20/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Green Building Final 6/20/2025 Approved NICHOLAS TROWBRIDGE
HVAC-Final 6/20/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Final 6/20/2025 Approved NICHOLAS TROWBRIDGE
Smoke Detectors 6/20/2025 Approved NICHOLAS TROWBRIDGE
Final 6/24/2025 OK to Issue CofO NICHOLAS TROWBRIDGE