16300 W STAGG ST 91406
Certificate Information: 16300 W STAGG ST 91406
- Application / Permit
- 23014-20000-04202
- Plan Check / Job No.
- B23VN14069
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (12) Metal Stamp Manufacturing
- Work Description
- INTERIOR AN EXTERIOR ALTERATION TO AN EXISTING 2 STORY BUILDING TO REVISE FLOOR LAY OUT REMOVE EXISTING STAIRS, INFILL EXISTING OPENING . SOME PARKING ALTERATIONS TO ACOMMAFDATE DISABLED ACCESS REQUIRMENTS . ADD NEW MECHANICAL EQUIPMENT
- Permit Issued
- Issued on 8/8/2024
- Issuing Office
- Current Status
- CofO Issued on 3/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2023 | MINA HABIB |
| Corrections Issued | 11/14/2023 | MINA HABIB |
| Quality Review Completed | 11/15/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 1/26/2024 | MINA HABIB |
| Applicant returned to address corrections | 2/5/2024 | MINA HABIB |
| Applicant returned to address corrections | 2/29/2024 | MINA HABIB |
| Applicant returned to address corrections | 3/27/2024 | MINA HABIB |
| Applicant returned to address corrections | 3/29/2024 | MINA HABIB |
| Applicant returned to address corrections | 4/2/2024 | MINA HABIB |
| Applicant returned to address corrections | 4/3/2024 | MINA HABIB |
| Applicant returned to address corrections | 4/8/2024 | MINA HABIB |
| Applicant returned to address corrections | 5/1/2024 | MINA HABIB |
| Applicant returned to address corrections | 5/22/2024 | MINA HABIB |
| Applicant returned to address corrections | 6/10/2024 | MINA HABIB |
| Applicant returned to address corrections | 6/13/2024 | MINA HABIB |
| Applicant returned to address corrections | 6/18/2024 | MINA HABIB |
| Applicant returned to address corrections | 6/20/2024 | MINA HABIB |
| Applicant returned to address corrections | 7/1/2024 | MINA HABIB |
| Applicant returned to address corrections | 7/8/2024 | MINA HABIB |
| Applicant returned to address corrections | 7/11/2024 | MINA HABIB |
| Applicant returned to address corrections | 7/17/2024 | MINA HABIB |
| Applicant returned to address corrections | 8/7/2024 | MINA HABIB |
| Plan Check Approved | 8/8/2024 | MINA HABIB |
| Issued | 8/8/2024 | APPLICANT |
| CofO in Progress | 3/10/2025 | DEANDRE HOFFMAN |
| Permit Finaled | 3/10/2025 | JEFFREY DURAN |
| CofO Issued | 3/10/2025 | JEFFREY DURAN |
| Permit Finaled | 3/10/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 12/1/2023 | RYAN LY |
| "T" removal | Cleared | 12/1/2023 | RYAN LY |
| Prkng lot landscape/Water mgmt | Cleared | 12/1/2023 | RYAN LY |
| Sewer availability | Cleared | 12/1/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/4/2023 | CARLOS AGUILERA |
| Green Code | Cleared | 3/13/2024 | MICHAEL AYERS |
| DAS Clearance | Cleared | 6/3/2024 | Farshad Alimohamadi |
Contact Information
| Architect | Swift,, Daniel R; Lic. No.: C32860 | 4601 WESTOWN PARKWAY SUITE 208 WEST DES MOINES, IA 50266 |
| Contractor | West Hills Construction Inc; Lic. No.: 578578-B | , |
| Engineer | Fong,, Darin; Lic. No.: S5188 | 3230 IMPERIAL HWY STE 302 BREA, CA 92821 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/12/2024 | Partial Inspection | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 8/16/2024 | Not Ready for Inspection | GREGORY POMISH |
| Excavation/Setback/Form/Re-Bar | 8/17/2024 | Partial Approval | GREGORY POMISH |
| Deputy Wood Construction | 9/13/2024 | Conditional Approval | DEANDRE HOFFMAN |
| Wood Frame | 9/13/2024 | Partial Inspection | DEANDRE HOFFMAN |
| Wood Frame | 9/23/2024 | Corrections Issued | DEANDRE HOFFMAN |
| Wood Frame | 10/21/2024 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 11/4/2024 | Partial Approval | DEANDRE HOFFMAN |
| Drywall Nailing | 11/13/2024 | Approved | DEANDRE HOFFMAN |
| Partition/T-Bar Ceiling | 12/16/2024 | Partial Inspection | DEANDRE HOFFMAN |
| Partition/T-Bar Ceiling | 12/17/2024 | Approved | DEANDRE HOFFMAN |
| Final | 2/25/2025 | OK to Issue CofO | DEANDRE HOFFMAN |
| Green Building Final | 2/25/2025 | Approved | DEANDRE HOFFMAN |
| Green Building Rough | 2/25/2025 | Approved | DEANDRE HOFFMAN |
| Reinforced Masonry Frame | 2/25/2025 | Approved | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 2/25/2025 | SGSOV Approved | DEANDRE HOFFMAN |
| Smoke Detectors | 2/25/2025 | Approved | DEANDRE HOFFMAN |