20152 W HARTLAND ST 91306

Certificate Information: 20152 W HARTLAND ST 91306

Application / Permit
23014-20000-04189
Plan Check / Job No.
B23VN14036
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW IRR. 19'-6" x 30'-11" ADDITION FOR NEW BEDROOM AND BATHROOM TO (E) SFD. ADD 12'-0" x 15'-7" ATTACHED TRELLIS. WORK PER ENGINEER.
Permit Issued
Issued on 3/19/2024
Issuing Office
Metro
Current Status
CofO Issued on 10/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/12/2023 APPLICANT
Assigned to Plan Check Engineer 10/19/2023 MIROOSH KHACHATOORIAN
Corrections Issued 10/20/2023 MIROOSH KHACHATOORIAN
Building Plans Picked Up 10/24/2023 APPLICANT
Applicant returned to address corrections 2/1/2024 ANGELICA DAVE
Plan Check Approved 2/7/2024 ISIS ARGUETA
Issued 3/19/2024 APPLICANT
CofO in Progress 10/22/2024 ARUTYUN MADATYAN
Permit Finaled 10/25/2024 JOHN JANSON
CofO Issued 10/25/2024 JOHN JANSON
Permit Finaled 10/25/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/18/2024 EDGAR ALCARAZ
Sewer availability Cleared 1/18/2024 EDGAR ALCARAZ
ZI Cleared 1/22/2024 ALEX VELA
Roof/Waste drainage to street Cleared 2/2/2024 EDGAR ALCARAZ

Contact Information

Contractor A R M Builders Inc; Lic. No.: 915352-B 1080 S LA CIENEGA #311      LOS ANGELES, CA 90035
Engineer Shakiban,, George; Lic. No.: C39908 23945 CALABASAS RD STE 101      CALABASAS, CA 91302

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/21/2024 Not Ready for Inspection ARUTYUN MADATYAN
Footing/Foundation/Slab 5/23/2024 Partial Approval ARUTYUN MADATYAN
Deputy Drilled-In Anchors 5/24/2024 Conditional Approval ALEXANDER HANDY
BUILDING-Rough-Frame 6/7/2024 Not Ready for Inspection ARUTYUN MADATYAN
Footing/Foundation/Slab 6/7/2024 Corrections Issued ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Corrections Issued ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 6/11/2024 Partial Approval ARUTYUN MADATYAN
PLUMBING-Rough 6/11/2024 Partial Inspection ARUTYUN MADATYAN
Deputy Wood Construction 6/25/2024 Conditional Approval ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 6/28/2024 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 7/1/2024 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 7/1/2024 Approved ARUTYUN MADATYAN
Green Building Rough 7/1/2024 Approved ARUTYUN MADATYAN
HVAC-Rough 7/1/2024 Approved ARUTYUN MADATYAN
PLUMBING-Rough 7/1/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 7/12/2024 Approved ARUTYUN MADATYAN
Shower Pan 7/12/2024 Approved ARUTYUN MADATYAN
Insulation 7/16/2024 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 7/22/2024 Approved ARUTYUN MADATYAN
Drywall Nailing 7/24/2024 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 9/20/2024 Approved DAVID SCANTLIN
Final 9/20/2024 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 9/20/2024 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 9/20/2024 Not Ready for Inspection DAVID SCANTLIN
HVAC-Final 9/20/2024 Approved DAVID SCANTLIN
PLUMBING-Final 9/20/2024 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 9/20/2024 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 9/20/2024 Approved DAVID SCANTLIN
Final 10/15/2024 Corrections Issued ARUTYUN MADATYAN
Footing/Foundation/Slab 10/15/2024 Approved ARUTYUN MADATYAN
Green Building Final 10/15/2024 Approved ARUTYUN MADATYAN
Final 10/21/2024 OK to Issue CofO ARUTYUN MADATYAN