18223-18225 W SUGARMAN ST 91356

Certificate Information: 18223-18225 W SUGARMAN ST 91356

Application / Permit
23014-20000-04146
Plan Check / Job No.
B23VN13909
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan Remodel and addition to existing single-family dwelling resulting in the creation of a New ADU per LAMC 12.22 A.33(c) and (e) *** BUILDING TO BE EQUIPPED WITH NFPA-13D FIRE SPRINKLERS THROUGH OUT***
Permit Issued
Issued on 2/21/2025
Issuing Office
Current Status
CofO in Progress on 4/15/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/30/2023 APPLICANT
Assigned to Plan Check Engineer 11/1/2023 DANIEL SMILEY
Corrections Issued 11/2/2023 DANIEL SMILEY
Plan Check Approved 2/4/2025 CRYSTEL MAALOUF
Issued 2/21/2025 APPLICANT
CofO in Progress 4/15/2026 JOHN KIDWELL

Permit Application Clearance Information

Low Impact Development (LID) Cleared 2/15/2024 MELINEH AGHAKHABIAN
Address approval Cleared 2/27/2024 BRYAN GODINEZ
Roof/Waste drainage to street Cleared 2/27/2024 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 3/4/2024 BRYAN GODINEZ
Sewer availability Cleared 3/4/2024 BRYAN GODINEZ
GPI Written Notices Cleared 2/4/2025 ROBERT PINA
Grading Pre-Inspection Cleared 2/4/2025 ROBERT PINA

Contact Information

Contractor Amin Farahpour; Lic. No.: 1079005-B       ,
Engineer Sayah,, Daniel H; Lic. No.: C67905 15233 VENTURA BLVD STE 1130      SHERMAN OAKS, CA 91403

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/23/2025 Partial Approval JOHN KIDWELL
Deputy Wood Construction 4/28/2025 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 4/30/2025 Not Ready for Inspection JOHN KIDWELL
Deputy Wood Construction 7/7/2025 Partial Approval JOHN KIDWELL
Interior/Exterior Lathing 7/25/2025 No Access for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 7/29/2025 Partial Approval JOHN KIDWELL
HVAC-Rough 7/29/2025 Approved JOHN KIDWELL
BUILDING-Rough-Frame 8/27/2025 Approved JOHN KIDWELL
ELECTRICAL-Rough 8/27/2025 Approved JOHN KIDWELL
Interior/Exterior Lathing 8/27/2025 Partial Approval JOHN KIDWELL
PLUMBING-Rough 8/27/2025 Approved JOHN KIDWELL
Shower Pan 8/27/2025 Not Ready for Inspection JOHN KIDWELL
Insulation 9/2/2025 Not Ready for Inspection SCOTT SOBEL
Shower Pan 9/2/2025 Approved SCOTT SOBEL
Insulation 9/3/2025 Corrections Issued SCOTT SOBEL
PLUMBING-Rough 9/3/2025 Corrections Issued SCOTT SOBEL
Shower Pan 9/3/2025 Approved SCOTT SOBEL
Insulation 9/9/2025 Not Ready for Inspection JOHN KIDWELL
Insulation 9/10/2025 Approved JOHN KIDWELL
PLUMBING-Rough 9/10/2025 Approved JOHN KIDWELL
Drywall Nailing 9/15/2025 Approved JOHN KIDWELL
Interior/Exterior Lathing 9/15/2025 Partial Approval JOHN KIDWELL
HVAC-Final 2/11/2026 Not Ready for Inspection JOHN KIDWELL
Service/Power Release 2/11/2026 Approved JOHN KIDWELL
Gas Test 2/12/2026 Approved JOHN KIDWELL
HVAC-Final 2/12/2026 Not Ready for Inspection JOHN KIDWELL
HVAC-Final 2/17/2026 Approved JOHN KIDWELL
Final 4/13/2026 OK to Issue CofO JOHN KIDWELL
Footing/Foundation/Slab 4/13/2026 Approved JOHN KIDWELL
PLUMBING-Final 4/13/2026 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 4/13/2026 SGSOV Approved JOHN KIDWELL
Smoke Detectors 4/13/2026 Approved JOHN KIDWELL
Special/Order Compliance 6/3/2026 Corrections Issued JOHN KIDWELL