6130-6132 N FALLBROOK AVE 91367

Certificate Information: 6130-6132 N FALLBROOK AVE 91367

Application / Permit
23014-20000-04137
Plan Check / Job No.
B23VN13883
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
33'-7" x 10'-0" ADDITION TO (E) SFD AND CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT (405 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22. WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 12/4/2023
Issuing Office
Valley
Current Status
CofO in Progress on 6/23/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/10/2023 APPLICANT
Assigned to Plan Check Engineer 10/13/2023 JEROME MAGAT PALMA
Corrections Issued 10/14/2023 JEROME MAGAT PALMA
Building Plans Picked Up 10/17/2023 APPLICANT
Issued 12/4/2023 APPLICANT
CofO in Progress 6/23/2026 GEVORK IPCHYAN

Permit Application Clearance Information

ZA Case Cleared 10/23/2023 ASHLEY RODARTE
Address approval Cleared 10/25/2023 COLIN LOREDO
Roof/Waste drainage to street Cleared 10/25/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/26/2023 COLIN LOREDO
Grading Pre-Inspection Cleared 10/30/2023 RUSSELL BONVOULOIR
Sewer availability Cleared 11/25/2023 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mobed,, Ashkan; Lic. No.: C92493 23450 KITTREDGE ST      WEST HILLS, CA 91307

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/15/2024 Corrections Issued GEVORK IPCHYAN
Underground Mechanical 5/16/2024 Approved GEVORK IPCHYAN
Footing/Foundation/Slab 5/17/2024 Approved GEVORK IPCHYAN
Deputy Drilled-In Anchors 6/6/2024 Conditional Approval GEVORK IPCHYAN
ELECTRICAL-Rough 6/7/2024 Partial Approval GEVORK IPCHYAN
HVAC-Rough 6/7/2024 Approved GEVORK IPCHYAN
Insulation 6/7/2024 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Rough 6/7/2024 Partial Approval GEVORK IPCHYAN
ELECTRICAL-Rough 6/20/2024 Approved GEVORK IPCHYAN
Insulation 6/20/2024 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 6/20/2024 Partial Approval GEVORK IPCHYAN
BUILDING-Rough-Frame 6/22/2024 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 6/22/2024 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/22/2024 Corrections Issued STEVEN BACK
HVAC-Rough 6/22/2024 Partial Approval STEVEN BACK
PLUMBING-Rough 6/22/2024 Not Ready for Inspection STEVEN BACK
Special/Order Compliance 6/22/2024 Approved STEVEN BACK
Deputy Wood Construction 6/24/2024 Conditional Approval GEVORK IPCHYAN
BUILDING-Rough-Frame 6/25/2024 Approved GEVORK IPCHYAN
ELECTRICAL-Rough 6/25/2024 Approved GEVORK IPCHYAN
Green Building Rough 6/25/2024 Approved GEVORK IPCHYAN
HVAC-Rough 6/25/2024 Approved GEVORK IPCHYAN
PLUMBING-Rough 6/25/2024 Approved GEVORK IPCHYAN
Drywall Nailing 6/28/2024 Approved MORRIS JACKSON
Interior/Exterior Lathing 6/28/2024 Approved MORRIS JACKSON
Shower Pan 6/28/2024 Not Ready for Inspection MORRIS JACKSON
Shower Pan 7/1/2024 Approved ALEXANDER HANDY
ELECTRICAL-Final 9/20/2024 Not Ready for Inspection GEVORK IPCHYAN
ELECTRICAL-Rough 9/20/2024 Not Ready for Inspection GEVORK IPCHYAN
HVAC-Final 9/20/2024 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Final 9/20/2024 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Rough 9/20/2024 Not Ready for Inspection GEVORK IPCHYAN
Deputy Wood Construction 9/26/2024 Conditional Approval GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/26/2024 Partial Approval GEVORK IPCHYAN
Rough-Elec/Plmb/HVAC 9/26/2024 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 10/3/2024 Partial Approval GEVORK IPCHYAN
Shower Pan 10/3/2024 Approved GEVORK IPCHYAN
Insulation 10/11/2024 Not Ready for Inspection TROY SANDERS
Insulation 10/15/2024 Approved TROY SANDERS
Drywall Nailing 10/18/2024 No Access for Inspection JEFFREY HARTLINE
ELECTRICAL-Final 4/7/2025 Not Ready for Inspection GEVORK IPCHYAN
Final 4/7/2025 Not Ready for Inspection GEVORK IPCHYAN
Green Building Final 4/7/2025 Partial Approval GEVORK IPCHYAN
HVAC-Final 4/7/2025 Partial Approval GEVORK IPCHYAN
PLUMBING-Final 4/7/2025 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 4/7/2025 SGSOV Approved GEVORK IPCHYAN
Smoke Detectors 4/7/2025 Approved GEVORK IPCHYAN
Final 6/22/2026 OK to Issue CofO GEVORK IPCHYAN
Green Building Final 6/22/2026 Approved GEVORK IPCHYAN
Service/Power Release 6/22/2026 Approved GEVORK IPCHYAN