923 W 58TH ST 90037

Certificate Information: 923 W 58TH ST 90037

Application / Permit
23014-20000-04124
Plan Check / Job No.
B23VN13831
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) 225 SF GARAGE + 141 SF IRREGULAR SHAPED ADDITION TO (N) 366 SF ADU PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP
Permit Issued
Issued on 2/8/2024
Issuing Office
Current Status
CofO Issued on 11/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2023 APPLICANT
Assigned to Plan Check Engineer 10/13/2023 DAVID CASTILLO
Corrections Issued 10/13/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 11/18/2023 DAVID CASTILLO
Plan Check Approved 11/21/2023 DAVID CASTILLO
Issued 2/8/2024 APPLICANT
CofO in Progress 10/15/2024 SABAS ALONSO
CofO Issued 11/1/2024 DEROLD HAUFF
Permit Finaled 11/1/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/30/2023 ARNULFO CHAMU
Roof/Waste drainage to street Cleared 10/30/2023 ARNULFO CHAMU
Eng Process Fee Ord 176,300 Cleared 11/15/2023 ARNULFO CHAMU
Sewer availability Cleared 11/15/2023 ARNULFO CHAMU

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/4/2024 Partial Inspection SABAS ALONSO
Underground Mechanical 4/16/2024 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 4/18/2024 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 4/23/2024 No Access for Inspection JOSE MACIAS
Excavation/Setback/Form/Re-Bar 5/3/2024 Approved SABAS ALONSO
Footing/Foundation/Slab 5/3/2024 Approved SABAS ALONSO
ELECTRICAL-Rough 5/13/2024 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/13/2024 Approved SABAS ALONSO
Sewer 5/13/2024 Approved SABAS ALONSO
Underground Mechanical 5/13/2024 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 5/15/2024 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 5/21/2024 Corrections Issued ANTHONY EGSON
Interior/Exterior Lathing 5/24/2024 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 5/29/2024 Approved SABAS ALONSO
ELECTRICAL-Rough 5/29/2024 Approved SABAS ALONSO
Green Building Rough 5/29/2024 Approved SABAS ALONSO
HVAC-Rough 5/29/2024 Approved SABAS ALONSO
PLUMBING-Rough 5/29/2024 Approved SABAS ALONSO
Insulation 5/31/2024 Corrections Issued JOSH MEISTER
Insulation 6/5/2024 Corrections Issued CRAIG DAVIS
Insulation 6/12/2024 Corrections Issued JOSE MACIAS
Drywall Nailing 7/3/2024 Approved SABAS ALONSO
Insulation 7/3/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 7/19/2024 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 7/22/2024 Approved SABAS ALONSO
Shower Pan 7/22/2024 Corrections Issued SABAS ALONSO
Shower Pan 7/30/2024 Approved SABAS ALONSO
Final 9/3/2024 Partial Inspection CRAIG DAVIS
Green Building Final 9/3/2024 Corrections Issued CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 9/3/2024 SGSOV Not Ready CRAIG DAVIS
Smoke Detectors 9/3/2024 Approved CRAIG DAVIS
Final 9/27/2024 Corrections Issued SABAS ALONSO
Green Building Final 9/27/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/27/2024 SGSOV Not Ready SABAS ALONSO
Final 10/8/2024 No Access for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 10/8/2024 SGSOV Not Ready SABAS ALONSO
Final 10/11/2024 OK to Issue CofO SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 10/11/2024 SGSOV Approved SABAS ALONSO