6014 N ALLOTT AVE 91401
Certificate Information: 6014 N ALLOTT AVE 91401
- Application / Permit
- 23014-20000-04115
- Plan Check / Job No.
- B23VN13806
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- IRREGULAR SIZED ADDT'N (642SF), ADD (N) PATIO COVER (280SF) AT REAR, ENCLOSE (E) PATIO COVER AT FRONT , REPLACE ROOF & MAJOR REMODEL TO (E) 1-STORY SFD (NFPA-13D FIRE SPRINKLERS THROUGHOUT) **ePlan**
- Permit Issued
- Issued on 1/4/2024
- Issuing Office
- Current Status
- CofO Issued on 11/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2023 | NILOOFAR MEHRAIN |
| Corrections Issued | 10/15/2023 | NILOOFAR MEHRAIN |
| Quality Review Completed | 10/16/2023 | STEVEN KIM |
| Plan Check Approved | 1/3/2024 | NILOOFAR MEHRAIN |
| Issued | 1/4/2024 | APPLICANT |
| CofO in Progress | 11/7/2025 | OGANES TARAKHCHYAN |
| CofO Issued | 11/13/2025 | RUBEN SALAS |
| Permit Finaled | 11/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 12/7/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 12/7/2023 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2023 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 12/8/2023 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/8/2024 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 2/12/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 2/21/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 3/5/2024 | Approved | JOSE AVILA |
| Insulation | 3/8/2024 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2024 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Deputy Wood Construction | 6/12/2024 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 6/13/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 6/13/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 6/13/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/24/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 7/9/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/9/2024 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/24/2024 | Approved | OGANES TARAKHCHYAN |
| Insulation | 7/24/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Insulation | 7/26/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 7/31/2024 | Approved | SALVADOR MARTINEZ |
| Shower Pan | 8/27/2024 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 9/10/2024 | Approved | OGANES TARAKHCHYAN |
| Pre-Inspection | 8/13/2025 | Corrections Issued | JACK KARGODORIAN |
| Final | 10/23/2025 | Partial Approval | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/23/2025 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 10/23/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 11/6/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |