6014 N ALLOTT AVE 91401

Certificate Information: 6014 N ALLOTT AVE 91401

Application / Permit
23014-20000-04115
Plan Check / Job No.
B23VN13806
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
IRREGULAR SIZED ADDT'N (642SF), ADD (N) PATIO COVER (280SF) AT REAR, ENCLOSE (E) PATIO COVER AT FRONT , REPLACE ROOF & MAJOR REMODEL TO (E) 1-STORY SFD (NFPA-13D FIRE SPRINKLERS THROUGHOUT) **ePlan**
Permit Issued
Issued on 1/4/2024
Issuing Office
Current Status
CofO Issued on 11/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/9/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 NILOOFAR MEHRAIN
Corrections Issued 10/15/2023 NILOOFAR MEHRAIN
Quality Review Completed 10/16/2023 STEVEN KIM
Plan Check Approved 1/3/2024 NILOOFAR MEHRAIN
Issued 1/4/2024 APPLICANT
CofO in Progress 11/7/2025 OGANES TARAKHCHYAN
CofO Issued 11/13/2025 RUBEN SALAS
Permit Finaled 11/13/2025 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 12/7/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 12/7/2023 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 12/8/2023 EDGAR ALCARAZ
Sewer availability Cleared 12/8/2023 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/8/2024 Approved JOSE AVILA
Footing/Foundation/Slab 2/12/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 2/21/2024 Corrections Issued KIRK SANDERS
PLUMBING-Rough 3/5/2024 Approved JOSE AVILA
Insulation 3/8/2024 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/12/2024 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 4/23/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/26/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Deputy Wood Construction 6/12/2024 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 6/13/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 6/13/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 6/13/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 6/24/2024 Not Ready for Inspection SALVADOR MARTINEZ
BUILDING-Rough-Frame 7/9/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/9/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 7/9/2024 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 7/24/2024 Approved OGANES TARAKHCHYAN
Insulation 7/24/2024 Corrections Issued OGANES TARAKHCHYAN
Insulation 7/26/2024 Approved OGANES TARAKHCHYAN
Drywall Nailing 7/31/2024 Approved SALVADOR MARTINEZ
Shower Pan 8/27/2024 Approved LOUIS ESCOTO
Interior/Exterior Lathing 9/10/2024 Approved OGANES TARAKHCHYAN
Pre-Inspection 8/13/2025 Corrections Issued JACK KARGODORIAN
Final 10/23/2025 Partial Approval OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 10/23/2025 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 10/23/2025 Approved OGANES TARAKHCHYAN
Final 11/6/2025 OK to Issue CofO OGANES TARAKHCHYAN