11471 W ALBERS ST 91601

Certificate Information: 11471 W ALBERS ST 91601

Application / Permit
23014-20000-04110
Plan Check / Job No.
B23VN13793
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
***ePlan** Addition to the Front and Rear of (E) Single Family Dwelling
Permit Issued
Issued on 3/26/2024
Issuing Office
Current Status
CofO Issued on 2/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/9/2023 APPLICANT
Assigned to Plan Check Engineer 10/13/2023 JOHNPAUL ISIP
Corrections Issued 10/16/2023 JOHNPAUL ISIP
Applicant returned to address corrections 11/28/2023 JOHNPAUL ISIP
Plan Check Approved 12/11/2023 EDWIN ESPIN
Issued 3/26/2024 APPLICANT
CofO in Progress 1/31/2025 CHRISTOPHER ROJAS
CofO in Progress 1/31/2025 CHRISTOPHER ROJAS
CofO in Progress 1/31/2025 CHRISTOPHER ROJAS
Permit Finaled 2/6/2025 RUBEN SALAS
CofO Issued 2/6/2025 RUBEN SALAS
Permit Finaled 2/6/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/19/2023 BRYAN GODINEZ
Sewer availability Cleared 10/19/2023 BRYAN GODINEZ
Low Impact Development (LID) Cleared 11/21/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 11/22/2023 BRYAN GODINEZ

Contact Information

Contractor Bg Construction & Remodeling Inc; Lic. No.: 817992-B       ,
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/23/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 4/24/2024 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 5/3/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 5/13/2024 Corrections Issued SALVADOR MARTINEZ
Pre-Inspection 5/13/2024 Partial Inspection SALVADOR MARTINEZ
BUILDING-Rough-Frame 5/15/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 5/15/2024 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 5/20/2024 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 5/20/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 5/23/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Insulation 5/23/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Deputy Wood Construction 6/13/2024 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 6/14/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 6/14/2024 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 6/25/2024 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 6/25/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 6/25/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 6/25/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 6/25/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 6/25/2024 Approved CHRISTOPHER ROJAS
Insulation 7/3/2024 Approved LEONARD ROSS II
Interior/Exterior Lathing 7/3/2024 Approved LEONARD ROSS II
Shower Pan 7/3/2024 Corrections Issued LEONARD ROSS II
Shower Pan 7/8/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 7/10/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/30/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 8/30/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Final 8/30/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 8/30/2024 Approved CHRISTOPHER ROJAS
HVAC-Final 8/30/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Final 8/30/2024 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 8/30/2024 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 8/30/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 9/6/2024 Approved CHRISTOPHER ROJAS
Final 9/6/2024 Partial Approval CHRISTOPHER ROJAS
HVAC-Final 9/6/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Final 9/6/2024 Approved CHRISTOPHER ROJAS
Final 1/31/2025 OK to Issue CofO CHRISTOPHER ROJAS