11471 W ALBERS ST 91601
Certificate Information: 11471 W ALBERS ST 91601
- Application / Permit
- 23014-20000-04110
- Plan Check / Job No.
- B23VN13793
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ***ePlan** Addition to the Front and Rear of (E) Single Family Dwelling
- Permit Issued
- Issued on 3/26/2024
- Issuing Office
- Current Status
- CofO Issued on 2/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2023 | JOHNPAUL ISIP |
| Corrections Issued | 10/16/2023 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 11/28/2023 | JOHNPAUL ISIP |
| Plan Check Approved | 12/11/2023 | EDWIN ESPIN |
| Issued | 3/26/2024 | APPLICANT |
| CofO in Progress | 1/31/2025 | CHRISTOPHER ROJAS |
| CofO in Progress | 1/31/2025 | CHRISTOPHER ROJAS |
| CofO in Progress | 1/31/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 2/6/2025 | RUBEN SALAS |
| CofO Issued | 2/6/2025 | RUBEN SALAS |
| Permit Finaled | 2/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2023 | BRYAN GODINEZ |
| Sewer availability | Cleared | 10/19/2023 | BRYAN GODINEZ |
| Low Impact Development (LID) | Cleared | 11/21/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 11/22/2023 | BRYAN GODINEZ |
Contact Information
| Contractor | Bg Construction & Remodeling Inc; Lic. No.: 817992-B | , |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/23/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/24/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 5/3/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 5/13/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Pre-Inspection | 5/13/2024 | Partial Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 5/15/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 5/15/2024 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/20/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Green Building Rough | 5/20/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Insulation | 5/23/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Deputy Wood Construction | 6/13/2024 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 6/14/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2024 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 6/25/2024 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 6/25/2024 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 6/25/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 6/25/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 6/25/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 7/3/2024 | Approved | LEONARD ROSS II |
| Interior/Exterior Lathing | 7/3/2024 | Approved | LEONARD ROSS II |
| Shower Pan | 7/3/2024 | Corrections Issued | LEONARD ROSS II |
| Shower Pan | 7/8/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 7/10/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 8/30/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 8/30/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 8/30/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 8/30/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 8/30/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 8/30/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 8/30/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 8/30/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 9/6/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 9/6/2024 | Partial Approval | CHRISTOPHER ROJAS |
| HVAC-Final | 9/6/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 9/6/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 1/31/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |