6236 N AGNES AVE 91606
Certificate Information: 6236 N AGNES AVE 91606
- Application / Permit
- 23014-20000-04105
- Plan Check / Job No.
- B23VN13781
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN Convert detached garage to ADU with an addition and (N) covered patio per ordinance. Existing recreation room to remain.
- Permit Issued
- Issued on 5/16/2024
- Issuing Office
- Current Status
- CofO Issued on 5/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2023 | WEIJIAN HUANG |
| Corrections Issued | 10/18/2023 | WEIJIAN HUANG |
| Applicant returned to address corrections | 1/31/2024 | ADAM HEGAZI |
| Plan Check Approved | 2/13/2024 | ADAM HEGAZI |
| Issued | 5/16/2024 | APPLICANT |
| CofO in Progress | 4/24/2025 | ROBERTO PALACIOS-LOPEZ |
| CofO Issued | 5/12/2025 | RUBEN SALAS |
| Permit Finaled | 5/12/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/16/2023 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 11/16/2023 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2023 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 11/30/2023 | EDGAR ALCARAZ |
Contact Information
| Contractor | Hofstadter Sheldon Douglas; Lic. No.: 684030-B | , |
| Contractor | Shell Burton Construction Inc; Lic. No.: 684030-B | , |
| Engineer | Zhang,, Yao; Lic. No.: NA74572 | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 6/17/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 6/17/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 6/17/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 6/20/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 6/20/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 6/20/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 6/20/2024 | Order to Comply Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/29/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 8/29/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| MERV13>=Rough | 8/29/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Deputy Wood Construction | 9/16/2024 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 10/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 10/7/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 10/7/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| MERV13>=Rough | 10/7/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 10/7/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 10/28/2024 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 10/28/2024 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 11/4/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 11/4/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 11/26/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 11/26/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Rough-Elec/Plmb/HVAC | 11/26/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 11/26/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 3/5/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 3/5/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 3/5/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 3/5/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| MERV13>=Final | 3/5/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 3/5/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/5/2025 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 3/5/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 4/7/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 4/7/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 4/7/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 4/7/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 4/7/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/7/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 4/24/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 4/24/2025 | Approved | ROBERTO PALACIOS-LOPEZ |