Certificate Information: 7058 N FIRMAMENT AVE 91406

Application / Permit
23014-20000-04089
Plan Check / Job No.
B23VN13722
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
IRREG SHAPED ADDITION TO AND CONVERT (E) REAR SFD TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 12/4/2023
Issuing Office
Valley
Current Status
Issued on 12/4/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/5/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 JEROME MAGAT PALMA
Corrections Issued 10/12/2023 JEROME MAGAT PALMA
Building Plans Picked Up 10/24/2023 APPLICANT
Plan Check Approved 11/29/2023 JESSE ARELLANO
Issued 12/4/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/16/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 11/16/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/21/2023 CARLOS AGUILERA
Sewer availability Cleared 11/21/2023 CARLOS AGUILERA

Contact Information

Contractor A.S Builders Group Inc; Lic. No.: 1030367-B 28202 SOMERSET COURT      CASTAIC, CA 91384

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/6/2024 Not Ready for Inspection RYAN SALAZAR
Pre-Inspection 2/8/2024 Corrections Issued CRAIG DAVIS
Gas Test 5/6/2024 Approved RYAN SALAZAR
PLUMBING-Rough 5/6/2024 Approved RYAN SALAZAR
HVAC-Rough 5/16/2024 Approved RYAN SALAZAR
Insulation 5/16/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 5/16/2024 Partial Approval RYAN SALAZAR
Drywall Nailing 6/25/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 8/22/2024 Approved RYAN SALAZAR
Final 8/22/2024 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 8/22/2024 Approved RYAN SALAZAR
Green Building Final 8/22/2024 Approved RYAN SALAZAR
Green Building Rough 8/22/2024 Approved RYAN SALAZAR
MERV13>=Final 8/22/2024 Approved RYAN SALAZAR
MERV13>=Rough 8/22/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 8/22/2024 SGSOV Approved RYAN SALAZAR
Smoke Detectors 8/22/2024 Approved RYAN SALAZAR