20226 W ALBION WAY 91326

Certificate Information: 20226 W ALBION WAY 91326

Application / Permit
23014-20000-04073
Plan Check / Job No.
B23VN13662
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition of Patio Cover (10' x 21'-10") with second story Patio Cover on top to existing two-story single family dwelling. NFPA 13D Fire Sprinklered Throughout.
Permit Issued
Issued on 1/11/2024
Issuing Office
Valley
Current Status
CofO Issued on 12/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/5/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 VAHAN JIVALAGIAN
Corrections Issued 10/20/2023 VAHAN JIVALAGIAN
Quality Review Completed 10/26/2023 OMID HEDAYAT
Building Plans Picked Up 10/27/2023 APPLICANT
Applicant returned to address corrections 1/9/2024 VAHAN JIVALAGIAN
Plan Check Approved 1/11/2024 VAHAN JIVALAGIAN
Issued 1/11/2024 APPLICANT
CofO in Progress 12/2/2024 JEFFREY PARD
CofO Issued 12/2/2024 JOHN JANSON
Permit Finaled 12/2/2024 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/4/2023 COLIN LOREDO
"T" removal Cleared 11/6/2023 STEVEN WECHSLER
Miscellaneous Cleared 11/6/2023 STEVEN WECHSLER
Miscellaneous Cleared 11/6/2023 STEVEN WECHSLER
Miscellaneous Cleared 11/6/2023 STEVEN WECHSLER
Miscellaneous Cleared 11/6/2023 STEVEN WECHSLER
ZA Case Cleared 11/6/2023 STEVEN WECHSLER
ZA Case Cleared 11/6/2023 STEVEN WECHSLER
Eng Process Fee Ord 176,300 Cleared 11/7/2023 COLIN LOREDO
GPI Written Notices Cleared 1/9/2024 VAHAN JIVALAGIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Mercado,, Lizandro; Lic. No.: S4331 27240 TURNBERRY LN STE 200      VALENCIA, CA 91355

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/22/2024 Not Ready for Inspection JEFFREY PARD
Excavation/Setback/Form/Re-Bar 2/28/2024 Not Ready for Inspection JEFFREY PARD
Footing/Foundation/Slab 2/28/2024 Not Ready for Inspection JEFFREY PARD
Deputy Drilled-In Anchors 2/29/2024 Conditional Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 3/5/2024 Approved JEFFREY PARD
BUILDING-Rough-Frame 5/7/2024 Partial Approval JEFFREY PARD
Green Building Rough 5/7/2024 Approved JEFFREY PARD
Verify Sprinkler Sign Off 5/7/2024 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 6/10/2024 Approved STEVEN BACK
Special/Order Compliance 6/10/2024 Corrections Issued STEVEN BACK
Verify Sprinkler Sign Off 6/10/2024 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 6/27/2024 Not Ready for Inspection JEFFREY PARD
Interior/Exterior Lathing 6/27/2024 Not Ready for Inspection JEFFREY PARD
Verify Sprinkler Sign Off 6/27/2024 Not Ready for Inspection JEFFREY PARD
Interior/Exterior Lathing 8/13/2024 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 11/8/2024 SGSOV Not Ready JEFFREY PARD
BUILDING-Rough-Frame 11/27/2024 Approved JEFFREY PARD
Drywall Nailing 11/27/2024 Approved JEFFREY PARD
Final 11/27/2024 OK to Issue CofO JEFFREY PARD
Footing/Foundation/Slab 11/27/2024 Approved JEFFREY PARD
Green Building Final 11/27/2024 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 11/27/2024 SGSOV Approved JEFFREY PARD
Smoke Detectors 11/27/2024 Approved JEFFREY PARD
Verify Sprinkler Sign Off 11/27/2024 Approved JEFFREY PARD