11053-11057 N WESCOTT AVE 91040

Certificate Information: 11053-11057 N WESCOTT AVE 91040

Application / Permit
23014-20000-04050
Plan Check / Job No.
B23VN13559
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. Partial conversion of ground floor of (E) SFD into an attached Accessory Dwelling Unit (830 SQFT) & Junior Accesory Dwelling Unit (488 SQFT) per CA Govt. Code 65852.2(e)(1)(A) and 65852.229. Scope includes addition of Trellis at rear with retention of SFD at 2nd level and partially at 1st (2,244 SQFT). All work per engineered plans. NFPA-13D fire sprinklers throughout.
Permit Issued
Issued on 3/10/2024
Issuing Office
Current Status
CofO Issued on 1/15/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2023 APPLICANT
Assigned to Plan Check Engineer 10/6/2023 MICHAEL LANZONE
Corrections Issued 10/7/2023 MICHAEL LANZONE
Applicant returned to address corrections 11/8/2023 DANIEL YIP
Applicant returned to address corrections 11/21/2023 DANIEL SMILEY
Plan Check Approved 12/14/2023 DANIEL SMILEY
Issued 3/10/2024 APPLICANT
CofO in Progress 12/10/2025 NICHOLAS TROWBRIDGE
CofO in Progress 12/29/2025 DAVID MATSON
CofO in Progress 1/15/2026 DAVID MATSON
CofO in Progress 1/15/2026 DAVID MATSON
Permit Finaled 1/15/2026 RUBEN SALAS
CofO Issued 1/15/2026 RUBEN SALAS
Permit Finaled 1/15/2026 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/13/2023 ROBERT HUGHES
Miscellaneous Cleared 10/16/2023 NELSON RODRIGUEZ
Address approval Cleared 10/18/2023 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 10/18/2023 EDGAR ALCARAZ
Sewer availability Cleared 10/18/2023 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 11/20/2023 EDGAR ALCARAZ
Flood clearance Cleared 12/7/2023 ABDULRAHMAN ALABTAH

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/18/2024 Partial Inspection WILLIAM WREN
Deputy Wood Construction 7/11/2024 Conditional Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 7/11/2024 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 7/24/2024 Not Ready for Inspection DAVID ANDERSON
Footing/Foundation/Slab 7/29/2024 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 8/6/2024 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Partial Approval WILLIAM WREN
Interior/Exterior Lathing 8/12/2024 Partial Approval WILLIAM WREN
PLUMBING-Rough 9/6/2024 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 9/9/2024 Partial Approval WILLIAM WREN
Pre-Inspection 9/10/2024 Partial Inspection WILLIAM WREN
PLUMBING-Rough 11/22/2024 Approved WILLIAM WREN
ELECTRICAL-Rough 1/31/2025 Approved WILLIAM WREN
Service/Power Release 2/5/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 2/12/2025 Corrections Issued WILLIAM WREN
FLOOD-Proofing Certificate 2/12/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 2/18/2025 Approved WILLIAM WREN
Insulation 3/26/2025 Corrections Issued WILLIAM WREN
Drywall Nailing 4/18/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 4/18/2025 Approved WILLIAM WREN
Shower Pan 4/18/2025 Approved WILLIAM WREN
Final 11/17/2025 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 11/17/2025 SGSOV Approved MATTHEW NELSON
Smoke Detectors 11/17/2025 Corrections Issued MATTHEW NELSON
Final 12/1/2025 Corrections Issued NICHOLAS TROWBRIDGE
Smoke Detectors 12/1/2025 Approved NICHOLAS TROWBRIDGE
Final 12/9/2025 Conditional Approval NICHOLAS TROWBRIDGE
Final 12/29/2025 Corrections Issued DAVID MATSON