10658 N LEV AVE 91345
Certificate Information: 10658 N LEV AVE 91345
- Application / Permit
- 23014-20000-04047
- Plan Check / Job No.
- B23VN13554
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ACCESSORY DWELLING UNIT ADDITION TO EXISTING DETACHED GARAGE AND REMOVE (E) CARPORT, DETACHED ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 5/31/2024
- Issuing Office
- Current Status
- CofO in Progress on 5/22/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2023 | CARLOS MONTES |
| Corrections Issued | 10/16/2023 | CARLOS MONTES |
| Quality Review Completed | 10/20/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 4/11/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 4/26/2024 | CARLOS MONTES |
| Plan Check Approved | 5/31/2024 | CARLOS MONTES |
| Issued | 5/31/2024 | APPLICANT |
| CofO in Progress | 5/22/2026 | JENNIFER RABUCHIN |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/22/2024 | RIDWAN HARDY |
| Address approval | Cleared | 4/3/2024 | KENIA CASTILLO |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2024 | KENIA CASTILLO |
| Sewer availability | Cleared | 4/4/2024 | KENIA CASTILLO |
| Low Impact Development (LID) | Cleared | 4/8/2024 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 4/15/2024 | KENIA CASTILLO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yaprak,, Taskin Tolga; Lic. No.: NA72927 | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/17/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 6/27/2024 | Approved | JENNIFER RABUCHIN |
| METHANE-Barrier | 6/27/2024 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 6/27/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/27/2024 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2024 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 7/17/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/4/2024 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 9/4/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 9/4/2024 | Not Ready for Inspection | MATTHEW NELSON |
| METHANE-Rough | 9/4/2024 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 9/11/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 9/11/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 9/11/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| METHANE-Rough | 9/11/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/11/2024 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 9/11/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 9/20/2024 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 9/20/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/20/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 9/30/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/30/2024 | Approved | JENNIFER RABUCHIN |
| Insulation | 9/30/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/18/2026 | Approved | JENNIFER RABUCHIN |
| Final | 3/18/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 3/18/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 3/18/2026 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 3/18/2026 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Rough | 3/18/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2026 | SGSOV Not Required | JENNIFER RABUCHIN |
| Smoke Detectors | 3/18/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/21/2026 | Approved | JENNIFER RABUCHIN |
| Final | 5/21/2026 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 5/21/2026 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 5/21/2026 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 5/21/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/21/2026 | Approved | JENNIFER RABUCHIN |