10947 N COLLETT AVE 91344

Certificate Information: 10947 N COLLETT AVE 91344

Application / Permit
23014-20000-04035
Plan Check / Job No.
B23VN13530
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (31'-9"x20'-0"), 1166 SQFT 1ST AND 2ND FLOOR ADDITION W/ 85 SQFT COVERED PATIO ADDITION TO THE EXISTING 1-STORY SINGLE FAMILY DWELLING W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 2/22/2024
Issuing Office
Valley
Current Status
CofO Issued on 12/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 PETER MOSESIAN
Corrections Issued 10/18/2023 PETER MOSESIAN
Quality Review Completed 10/27/2023 OMID HEDAYAT
Building Plans Picked Up 11/1/2023 APPLICANT
Applicant returned to address corrections 12/1/2023 PETER MOSESIAN
Plan Check Approved 2/21/2024 PETER MOSESIAN
Issued 2/22/2024 APPLICANT
CofO in Progress 12/6/2024 JAVIER RAMOS JR
CofO Issued 12/18/2024 RUBEN SALAS
Permit Finaled 12/18/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/2/2023 CARLOS RAMIREZ
Sewer availability Cleared 11/2/2023 CARLOS RAMIREZ
Hydrant and Access approval Cleared 11/26/2023 RUEL COLE
Low Impact Development (LID) Cleared 2/9/2024 MITESH PATEL
Roof/Waste drainage to street Cleared 2/12/2024 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Segovia,, Felipe; Lic. No.: C41102 2622 DORSET DR      TORRANCE, CA 90503

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 3/12/2024 Approved JOHN COLEMAN
Underground Mechanical 3/12/2024 Approved JOHN COLEMAN
Deputy Drilled-In Anchors 3/15/2024 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 3/18/2024 Not Ready for Inspection KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 3/21/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 3/21/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/29/2024 Partial Approval JAVIER RAMOS JR
Deputy Wood Construction 4/3/2024 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 4/10/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 4/19/2024 Approved MISAEL ESPARZA
ELECTRICAL-Rough 4/22/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/22/2024 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 5/6/2024 Corrections Issued JOHN COLEMAN
HVAC-Rough 5/6/2024 Approved JOHN COLEMAN
BUILDING-Rough-Frame 5/8/2024 Partial Inspection JAVIER RAMOS JR
Service/Power Release 5/8/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 5/28/2024 Approved JAVIER RAMOS JR
Green Building Rough 5/28/2024 Approved JAVIER RAMOS JR
Insulation 5/28/2024 Corrections Issued JAVIER RAMOS JR
MERV13>=Rough 5/28/2024 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 5/28/2024 Approved JAVIER RAMOS JR
Drywall Nailing 6/3/2024 Approved JAVIER RAMOS JR
Insulation 6/3/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/7/2024 Approved JAVIER RAMOS JR
Shower Pan 6/7/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 8/23/2024 Corrections Issued JAVIER RAMOS JR
Final 8/23/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 8/23/2024 Approved JAVIER RAMOS JR
MERV13>=Final 8/23/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/23/2024 SGSOV Not Ready JAVIER RAMOS JR
Smoke Detectors 8/23/2024 Approved JAVIER RAMOS JR
Final 9/12/2024 Corrections Issued JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 9/12/2024 SGSOV Approved JACK KARGODORIAN
Final 9/18/2024 Corrections Issued MATTHEW NELSON
ELECTRICAL-Final 12/5/2024 Approved JAVIER RAMOS JR
Final 12/5/2024 OK to Issue CofO JAVIER RAMOS JR
Service/Power Release 12/5/2024 Approved JAVIER RAMOS JR