10947 N COLLETT AVE 91344
Certificate Information: 10947 N COLLETT AVE 91344
- Application / Permit
- 23014-20000-04035
- Plan Check / Job No.
- B23VN13530
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (31'-9"x20'-0"), 1166 SQFT 1ST AND 2ND FLOOR ADDITION W/ 85 SQFT COVERED PATIO ADDITION TO THE EXISTING 1-STORY SINGLE FAMILY DWELLING W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 2/22/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2023 | PETER MOSESIAN |
| Corrections Issued | 10/18/2023 | PETER MOSESIAN |
| Quality Review Completed | 10/27/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 11/1/2023 | APPLICANT |
| Applicant returned to address corrections | 12/1/2023 | PETER MOSESIAN |
| Plan Check Approved | 2/21/2024 | PETER MOSESIAN |
| Issued | 2/22/2024 | APPLICANT |
| CofO in Progress | 12/6/2024 | JAVIER RAMOS JR |
| CofO Issued | 12/18/2024 | RUBEN SALAS |
| Permit Finaled | 12/18/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2023 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 11/2/2023 | CARLOS RAMIREZ |
| Hydrant and Access approval | Cleared | 11/26/2023 | RUEL COLE |
| Low Impact Development (LID) | Cleared | 2/9/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 2/12/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Segovia,, Felipe; Lic. No.: C41102 | 2622 DORSET DR TORRANCE, CA 90503 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 3/12/2024 | Approved | JOHN COLEMAN |
| Underground Mechanical | 3/12/2024 | Approved | JOHN COLEMAN |
| Deputy Drilled-In Anchors | 3/15/2024 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 3/18/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 3/21/2024 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 3/21/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2024 | Partial Approval | JAVIER RAMOS JR |
| Deputy Wood Construction | 4/3/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/19/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/22/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/22/2024 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/6/2024 | Corrections Issued | JOHN COLEMAN |
| HVAC-Rough | 5/6/2024 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 5/8/2024 | Partial Inspection | JAVIER RAMOS JR |
| Service/Power Release | 5/8/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/28/2024 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 5/28/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 5/28/2024 | Corrections Issued | JAVIER RAMOS JR |
| MERV13>=Rough | 5/28/2024 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 5/28/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 6/3/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 6/3/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/7/2024 | Approved | JAVIER RAMOS JR |
| Shower Pan | 6/7/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 8/23/2024 | Corrections Issued | JAVIER RAMOS JR |
| Final | 8/23/2024 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 8/23/2024 | Approved | JAVIER RAMOS JR |
| MERV13>=Final | 8/23/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 8/23/2024 | SGSOV Not Ready | JAVIER RAMOS JR |
| Smoke Detectors | 8/23/2024 | Approved | JAVIER RAMOS JR |
| Final | 9/12/2024 | Corrections Issued | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 9/12/2024 | SGSOV Approved | JACK KARGODORIAN |
| Final | 9/18/2024 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Final | 12/5/2024 | Approved | JAVIER RAMOS JR |
| Final | 12/5/2024 | OK to Issue CofO | JAVIER RAMOS JR |
| Service/Power Release | 12/5/2024 | Approved | JAVIER RAMOS JR |