18613 W MALDEN ST 91324

Certificate Information: 18613 W MALDEN ST 91324

Application / Permit
23014-20000-04012
Plan Check / Job No.
B23VN13401
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. Addition to (E) SFD with new patio. EPLAN 344 S.F. ADDITION TO EXISTING SINGLE FAMILY DWELLING (833 S.F.) AND PROPOSED NEW PATIO 261 S.F.
Permit Issued
Issued on 6/11/2024
Issuing Office
Current Status
CofO Issued on 6/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2023 APPLICANT
Assigned to Plan Check Engineer 10/4/2023 MICHAEL LANZONE
Corrections Issued 10/4/2023 MICHAEL LANZONE
Applicant returned to address corrections 4/24/2024 KELVIN CHUONG
Applicant returned to address corrections 4/25/2024 KELVIN CHUONG
Plan Check Approved 5/4/2024 KELVIN CHUONG
Plan Check Approved 6/11/2024 CHRISTOPHER KOMANCHECK
Issued 6/11/2024 APPLICANT
CofO in Progress 5/22/2025 KRISTEN BEVERIDGE
Permit Finaled 6/17/2025 JOHN JANSON
CofO Issued 6/17/2025 JOHN JANSON
Permit Finaled 6/17/2025 JOHN JANSON

Permit Application Clearance Information

Low Impact Development (LID) Cleared 4/8/2024 TOMMY YIN
Eng Process Fee Ord 176,300 Cleared 4/9/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 4/12/2024 TAL SHEMEN

Contact Information

Architect Sadekyan,, Hamlet; Lic. No.: C39815 1950 CHILTON DR      GLENDALE, CA 91201
Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/12/2024 Partial Approval KRISTEN CAUSEY
Deputy Drilled-In Anchors 7/17/2024 Conditional Approval DAVID SCANTLIN
Footing/Foundation/Slab 8/13/2024 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 8/29/2024 Partial Approval KRISTEN CAUSEY
ELECTRICAL-Rough 9/18/2024 Approved KRISTEN CAUSEY
PLUMBING-Rough 9/18/2024 Approved KRISTEN CAUSEY
Deputy Wood Construction 9/19/2024 Conditional Approval KRISTEN CAUSEY
Insulation 9/24/2024 Corrections Issued KRISTEN CAUSEY
Interior/Exterior Lathing 9/24/2024 Partial Approval KRISTEN CAUSEY
Shower Pan 9/24/2024 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 10/1/2024 Approved KRISTEN CAUSEY
Drywall Nailing 10/1/2024 Approved KRISTEN CAUSEY
Green Building Rough 10/1/2024 Approved KRISTEN CAUSEY
Smoke Detectors 3/12/2025 Not Ready for Inspection KRISTEN CAUSEY
Final 4/8/2025 Corrections Issued DAVID SCANTLIN
Green Building Final 4/8/2025 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 4/8/2025 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 4/8/2025 Approved DAVID SCANTLIN
Final 4/11/2025 Partial Inspection KRISTEN CAUSEY
ELECTRICAL-Final 4/23/2025 Approved KRISTEN CAUSEY
Final 4/23/2025 Conditional Approval KRISTEN CAUSEY
HVAC-Final 4/23/2025 Approved KRISTEN CAUSEY
PLUMBING-Final 4/23/2025 Approved KRISTEN CAUSEY
Final 5/21/2025 OK to Issue CofO KRISTEN CAUSEY