13403 W LOCHRIN LANE 91342
Certificate Information: 13403 W LOCHRIN LANE 91342
- Application / Permit
- 23014-20000-03965
- Plan Check / Job No.
- B23VN13283
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: ENLCOSE (E) 16 'X 25' PATIO COVER FOR HABITABLE SPACE AND 8'-8" X 12'-0" ADDITION TO (E) SFD. ALL WORK PER ENG. " COMPLY WITH DEPARTMENT ORDER effective date 03/30/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 11/16/2023
- Issuing Office
- Current Status
- CofO Issued on 3/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 10/2/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 11/7/2023 | LUISANGEL VALENZUELA |
| Issued | 11/16/2023 | APPLICANT |
| CofO in Progress | 2/29/2024 | CHRISTOPHER ROJAS |
| Permit Finaled | 3/8/2024 | RUBEN SALAS |
| CofO Issued | 3/8/2024 | RUBEN SALAS |
| Permit Finaled | 3/8/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/21/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 10/21/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2023 | TAL SHEMEN |
| Grading Pre-Inspection | Cleared | 10/31/2023 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gosen,, James; Lic. No.: NA43590 | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/28/2023 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 11/29/2023 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 12/8/2023 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 12/8/2023 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 12/8/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 12/20/2023 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 12/20/2023 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 12/20/2023 | Approved | KEVIN BERBERYAN |
| Insulation | 12/20/2023 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 12/20/2023 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 12/26/2023 | Approved | KEVIN BERBERYAN |
| Final | 1/24/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 1/24/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 1/24/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 1/26/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 1/26/2024 | Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 1/26/2024 | Approved | CHRISTOPHER ROJAS |