6601 N CLYBOURN AVE 91606

Certificate Information: 6601 N CLYBOURN AVE 91606

Application / Permit
23014-20000-03963
Plan Check / Job No.
B23VN13267
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. ground floor addition to (E) 1-story SFD. All work per WFPP. R3 occupancy NFPA 13D sprinklered throughout
Permit Issued
Issued on 2/12/2024
Issuing Office
Current Status
CofO Issued on 7/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2023 APPLICANT
Assigned to Plan Check Engineer 10/3/2023 MICHAEL LANZONE
Corrections Issued 10/3/2023 MICHAEL LANZONE
Applicant returned to address corrections 1/24/2024 KELVIN CHUONG
Plan Check Approved 1/30/2024 KELVIN CHUONG
Issued 2/12/2024 APPLICANT
CofO in Progress 7/3/2025 JOSE AVILA
CofO Issued 7/30/2025 RUBEN SALAS
Permit Finaled 7/30/2025 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 1/12/2024 ROGELIO CORTES
Roof/Waste drainage to street Cleared 1/13/2024 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 1/16/2024 JOHN LIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/3/2024 Conditional Approval ROBERT GOLD
Pre-Inspection 6/11/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Underground Mechanical 6/11/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Deputy Drilled-In Anchors 6/14/2024 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 6/17/2024 Approved ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 6/17/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Sewer 6/17/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Underground Mechanical 6/17/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 7/9/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Rough 7/9/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 7/9/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Wood Frame 7/9/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 7/11/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Wood Frame 7/11/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Green Building Rough 7/15/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Structural Steel Frame 7/15/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 7/16/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Structural Steel Frame 7/16/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Wood Frame 7/16/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Wood Frame 7/31/2024 Corrections Issued JENNIFER RABUCHIN
Deputy Wood Construction 8/1/2024 Conditional Approval DAVID MATSON
Wood Frame 8/2/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/6/2024 Corrections Issued JACK KARGODORIAN
Green Building Rough 8/6/2024 Not Ready for Inspection JACK KARGODORIAN
Footing/Foundation/Slab 8/8/2024 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 8/20/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Wood Frame 8/20/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 8/23/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Wood Frame 8/23/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/26/2024 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/26/2024 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 10/3/2024 Corrections Issued JOSE AVILA
Sewer 10/3/2024 Approved JOSE AVILA
ELECTRICAL-Rough 10/11/2024 Not Ready for Inspection JOSE AVILA
Interior/Exterior Lathing 10/17/2024 Approved JOSE AVILA
PLUMBING-Rough 10/17/2024 Approved JOSE AVILA
ELECTRICAL-Rough 10/23/2024 No Access for Inspection JOSE AVILA
ELECTRICAL-Rough 10/24/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 11/6/2024 Approved JOSE AVILA
ELECTRICAL-Rough 11/6/2024 Approved JOSE AVILA
Green Building Rough 11/6/2024 Approved JOSE AVILA
HVAC-Rough 11/6/2024 Approved JOSE AVILA
Green Building Rough 11/21/2024 Approved JOSE AVILA
Insulation 11/21/2024 Approved JOSE AVILA
Drywall Nailing 11/26/2024 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 12/11/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 1/8/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 4/28/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Final 5/7/2025 Approved JOSE AVILA
HVAC-Final 5/19/2025 Corrections Issued JOSE AVILA
PLUMBING-Final 5/19/2025 Approved JOSE AVILA
Green Building Final 6/16/2025 Approved JOSE AVILA
HVAC-Final 6/16/2025 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 6/16/2025 SGSOV Approved JOSE AVILA
Smoke Detectors 6/16/2025 Approved JOSE AVILA
Final 7/2/2025 OK to Issue CofO JOSE AVILA