12644-12646 N COMETA AVE 91340

Certificate Information: 12644-12646 N COMETA AVE 91340

Application / Permit
23014-20000-03928
Plan Check / Job No.
B23VN13131
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan New attached ADU and covered patio addition at rear of (E) 1-story S.F.D. w/att Garage per ordinance, and new addition to SFD
Permit Issued
Issued on 2/14/2024
Issuing Office
Current Status
Issued on 2/14/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/26/2023 APPLICANT
Assigned to Plan Check Engineer 9/29/2023 MINA HABILI
Corrections Issued 10/2/2023 MINA HABILI
Applicant returned to address corrections 1/11/2024 MINA HABILI
Applicant returned to address corrections 2/6/2024 MINA HABILI
Applicant returned to address corrections 2/8/2024 KELVIN CHUONG
Plan Check Approved 2/14/2024 MINA HABILI
Issued 2/14/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/7/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/10/2023 COLIN LOREDO
Sewer availability Cleared 10/10/2023 COLIN LOREDO
Miscellaneous Cleared 11/13/2023 CASEY JENSEN
Low Impact Development (LID) Cleared 12/27/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 1/8/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/19/2024 Approved KEVIN BERBERYAN
Pre-Inspection 3/20/2024 Partial Inspection KEVIN BERBERYAN
Deputy Drilled-In Anchors 3/22/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 3/28/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 5/30/2024 Partial Approval KEVIN BERBERYAN
Green Building Rough 5/30/2024 Not Ready for Inspection KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 7/1/2024 Conditional Approval KEVIN BERBERYAN
Wood Frame 7/1/2024 Partial Approval KEVIN BERBERYAN
Deputy Wood Construction 7/2/2024 Conditional Approval ROBERT GOLD
PLUMBING-Rough 7/12/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 7/31/2024 Approved KEVIN BERBERYAN
HVAC-Rough 7/31/2024 Corrections Issued KEVIN BERBERYAN
Wood Frame 7/31/2024 Corrections Issued KEVIN BERBERYAN
Insulation 8/15/2024 Conditional Approval KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 8/21/2024 Not Ready for Inspection WILLIAM WREN
Interior/Exterior Lathing 8/21/2024 Partial Approval WILLIAM WREN
Drywall Nailing 9/24/2024 Conditional Approval KEVIN BERBERYAN
Sewer 9/24/2024 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 10/1/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 12/20/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 12/20/2024 Approved MICHEL ABAJAN
Final 12/20/2024 Corrections Issued MICHEL ABAJAN
Green Building Final 12/20/2024 Approved MICHEL ABAJAN
Green Building Rough 12/20/2024 Approved MICHEL ABAJAN
HVAC-Final 12/20/2024 Approved MICHEL ABAJAN
PLUMBING-Final 12/20/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/20/2024 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 12/20/2024 Approved MICHEL ABAJAN
Final 2/19/2025 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 2/19/2025 SGSOV Not Ready KEVIN BERBERYAN
Final 3/5/2025 Corrections Issued KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 3/5/2025 SGSOV Approved KEVIN BERBERYAN