3848-3850 S WALL ST 90011
Certificate Information: 3848-3850 S WALL ST 90011
- Application / Permit
- 23014-20000-03898
- Plan Check / Job No.
- B23VN13028
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN INTERIOR REMODEL, PROVIDE LANDING IN REAR, REPAIR/ REPLACE PORTION OF ROOF OF (E) DUPLEX ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 1/23/2024
- Issuing Office
- Current Status
- CofO in Progress on 7/11/2025
Permit Application Status History
| Submitted | 9/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2023 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 10/11/2023 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 10/23/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 11/8/2023 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 12/29/2023 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 1/22/2024 | SEWADA ZADOORAN MILAGARDI |
| Issued | 1/23/2024 | APPLICANT |
| CofO in Progress | 7/1/2025 | ALEJANDRO DE ARTOLA |
| No Progress | 7/11/2025 | SCOTT FINNILA |
| CofO in Progress | 7/11/2025 | SCOTT FINNILA |
Permit Application Clearance Information
| Address approval | Cleared | 11/4/2023 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 11/4/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 11/4/2023 | TREVOR QUAN |
| Historic Resource Verification | Cleared | 11/6/2023 | RAFAEL FONTES |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2023 | TREVOR QUAN |
| Redevelopment Project Area | Cleared | 11/9/2023 | YASMINE BASHIRI |
| Hydrant and Access approval | Cleared | 12/22/2023 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Javier; Lic. No.: C76510 | 2705 S FREMONT AVE APT D ALHAMBRA, CA 91803 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/16/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Deputy Drilled-In Anchors | 6/11/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Sewer | 7/1/2024 | Approved | ANTHONY EGSON |
| Wood Frame | 7/1/2024 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 9/9/2024 | Partial Approval | MICHAEL LEWIS |
| Insulation | 9/10/2024 | Partial Approval | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2024 | Partial Approval | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/11/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/11/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/15/2024 | Corrections Issued | BRENDAN MORELLI |
| HVAC-Rough | 10/15/2024 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 10/15/2024 | Corrections Issued | BRENDAN MORELLI |
| Interior/Exterior Lathing | 10/29/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 10/29/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/30/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/30/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/30/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/30/2024 | Approved | ALEJANDRO DE ARTOLA |
| Shower Pan | 12/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 12/9/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/7/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/13/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 1/13/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 1/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 5/16/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 6/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 6/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 6/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 6/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 6/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 6/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 6/17/2025 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 6/17/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 6/30/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 6/30/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 6/30/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 6/30/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 6/30/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 6/30/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 6/30/2025 | Approved | ALEJANDRO DE ARTOLA |