3848-3850 S WALL ST 90011

Certificate Information: 3848-3850 S WALL ST 90011

Application / Permit
23014-20000-03898
Plan Check / Job No.
B23VN13028
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN INTERIOR REMODEL, PROVIDE LANDING IN REAR, REPAIR/ REPLACE PORTION OF ROOF OF (E) DUPLEX ALL WORK PER ENGINEERING
Permit Issued
Issued on 1/23/2024
Issuing Office
Current Status
CofO in Progress on 7/11/2025

Permit Application Status History

Submitted 9/25/2023 APPLICANT
Assigned to Plan Check Engineer 10/5/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 10/11/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 10/23/2023 OMID HEDAYAT
Applicant returned to address corrections 11/8/2023 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 12/29/2023 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 1/22/2024 SEWADA ZADOORAN MILAGARDI
Issued 1/23/2024 APPLICANT
CofO in Progress 7/1/2025 ALEJANDRO DE ARTOLA
No Progress 7/11/2025 SCOTT FINNILA
CofO in Progress 7/11/2025 SCOTT FINNILA

Permit Application Clearance Information

Address approval Cleared 11/4/2023 TREVOR QUAN
Roof/Waste drainage to street Cleared 11/4/2023 TREVOR QUAN
Sewer availability Cleared 11/4/2023 TREVOR QUAN
Historic Resource Verification Cleared 11/6/2023 RAFAEL FONTES
Eng Process Fee Ord 176,300 Cleared 11/7/2023 TREVOR QUAN
Redevelopment Project Area Cleared 11/9/2023 YASMINE BASHIRI
Hydrant and Access approval Cleared 12/22/2023 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Javier; Lic. No.: C76510 2705 S FREMONT AVE APT D      ALHAMBRA, CA 91803

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/16/2024 Conditional Approval ALEJANDRO DE ARTOLA
Deputy Drilled-In Anchors 6/11/2024 Conditional Approval ALEJANDRO DE ARTOLA
Sewer 7/1/2024 Approved ANTHONY EGSON
Wood Frame 7/1/2024 Corrections Issued ANTHONY EGSON
Wood Frame 9/9/2024 Partial Approval MICHAEL LEWIS
Insulation 9/10/2024 Partial Approval CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 9/12/2024 Partial Approval CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 10/9/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 10/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/15/2024 Corrections Issued BRENDAN MORELLI
HVAC-Rough 10/15/2024 Approved BRENDAN MORELLI
PLUMBING-Rough 10/15/2024 Corrections Issued BRENDAN MORELLI
Interior/Exterior Lathing 10/29/2024 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 10/29/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/30/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/30/2024 Approved ALEJANDRO DE ARTOLA
Green Building Rough 10/30/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/30/2024 Approved ALEJANDRO DE ARTOLA
Shower Pan 12/4/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 12/9/2024 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/7/2025 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/13/2025 Approved ALEJANDRO DE ARTOLA
Insulation 1/13/2025 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 1/17/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 5/16/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/17/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 6/17/2025 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 6/17/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 6/17/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 6/17/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 6/17/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 6/17/2025 SGSOV Approved ALEJANDRO DE ARTOLA
Smoke Detectors 6/17/2025 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 6/30/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/30/2025 Approved ALEJANDRO DE ARTOLA
Final 6/30/2025 OK to Issue CofO ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 6/30/2025 Approved ALEJANDRO DE ARTOLA
Green Building Final 6/30/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 6/30/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 6/30/2025 Approved ALEJANDRO DE ARTOLA