6330 N COSTELLO AVE 91401
Certificate Information: 6330 N COSTELLO AVE 91401
- Application / Permit
- 23014-20000-03862
- Plan Check / Job No.
- B23VN12931
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan CONVERT 360 SF GARAGE WITH ADDITION TO REAR 432 SF TO ADU 792 SF PER STATE LAW
- Permit Issued
- Issued on 10/26/2023
- Issuing Office
- Current Status
- CofO Issued on 8/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2023 | KHUONG TRUONG |
| Corrections Issued | 9/27/2023 | KHUONG TRUONG |
| Applicant returned to address corrections | 10/11/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 10/17/2023 | KHUONG TRUONG |
| Issued | 10/26/2023 | APPLICANT |
| CofO in Progress | 7/1/2024 | RYAN SALAZAR |
| Permit Finaled | 8/26/2024 | DANIEL ORRANTE |
| CofO Issued | 8/26/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/26/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/5/2023 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 10/5/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/11/2023 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 10/11/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/22/2024 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 2/22/2024 | Partial Approval | RYAN SALAZAR |
| Pre-Inspection | 2/22/2024 | Partial Inspection | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 2/26/2024 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 2/27/2024 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 2/27/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 3/12/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2024 | Partial Approval | RYAN SALAZAR |
| Gas Test | 3/12/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Rough | 3/12/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Sewer | 3/12/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Gas Test | 3/14/2024 | Approved | RYAN SALAZAR |
| Sewer | 3/14/2024 | Partial Approval | RYAN SALAZAR |
| Sewer | 3/18/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 4/4/2024 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Rough | 4/4/2024 | Approved | RYAN SALAZAR |
| Gas Test | 4/4/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 4/4/2024 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 4/4/2024 | Approved | RYAN SALAZAR |
| Insulation | 4/9/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 4/12/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 5/9/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 6/21/2024 | No Access for Inspection | JOHN COLEMAN |
| Final | 6/21/2024 | No Access for Inspection | JOHN COLEMAN |
| Green Building Final | 6/21/2024 | Approved | JOHN COLEMAN |
| Green Building Rough | 6/21/2024 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 6/21/2024 | SGSOV Not Ready | JOHN COLEMAN |
| Smoke Detectors | 6/21/2024 | No Access for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 6/25/2024 | Approved | RYAN SALAZAR |
| Final | 6/25/2024 | OK to Issue CofO | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 6/25/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 6/25/2024 | Approved | RYAN SALAZAR |
| Service/Power Release | 6/26/2024 | Approved | RYAN SALAZAR |