9457-9459 N CORDERO AVE 91042

Certificate Information: 9457-9459 N CORDERO AVE 91042

Application / Permit
23014-20000-03857
Plan Check / Job No.
B23VN12925
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN PROPOSED 26'-4" X 28'-11" IRREGULAR SHAPED ADDITION TO (E) SFD TO CREATE ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e) AND ATTACH GARAGE TO CREATE 1 BUILDING. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/30/2024
Issuing Office
Current Status
CofO Issued on 11/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2023 APPLICANT
Assigned to Plan Check Engineer 10/5/2023 RAPHAEL ROSAS
Corrections Issued 10/11/2023 RAPHAEL ROSAS
Quality Review Completed 10/12/2023 STEVEN KIM
Applicant returned to address corrections 10/25/2023 RAPHAEL ROSAS
Applicant returned to address corrections 9/19/2024 RAPHAEL ROSAS
Plan Check Approved 9/30/2024 RAPHAEL ROSAS
Issued 9/30/2024 APPLICANT
CofO in Progress 10/3/2025 DAVID ANDERSON
Permit Finaled 11/14/2025 RUBEN SALAS
CofO Issued 11/14/2025 RUBEN SALAS
Permit Finaled 11/14/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/29/2024 CARLOS RAMIREZ
BHO/Hillside ordinance Cleared 4/29/2024 CARLOS RAMIREZ
BHO/Hillside ordinance Cleared 4/29/2024 CARLOS RAMIREZ
BHO/Hillside ordinance Cleared 4/29/2024 CARLOS RAMIREZ
BHO/Hillside ordinance Cleared 4/29/2024 CARLOS RAMIREZ
BHO/Hillside ordinance Cleared 4/29/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 5/1/2024 CARLOS RAMIREZ
Sewer availability Cleared 5/1/2024 CARLOS RAMIREZ
Distance to fire station Cleared 7/24/2024 LAVEON RIDER
Hydrant and Access approval Cleared 7/24/2024 LAVEON RIDER
Specific Plan Cleared 8/28/2024 JOSHUA ORDONEZ
ZI Cleared 8/28/2024 JOSHUA ORDONEZ
Low Impact Development (LID) Cleared 9/12/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 9/12/2024 CARLOS RAMIREZ
GPI Written Notices Cleared 9/19/2024 RAPHAEL ROSAS
Grading Pre-Inspection Cleared 9/19/2024 CHARLES POWELL

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng D; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/10/2024 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 12/16/2024 Approved DAVID ANDERSON
Special/Order Compliance 12/16/2024 Corrections Issued DAVID ANDERSON
Underground Mechanical 1/24/2025 Partial Approval DAVID ANDERSON
ELECTRICAL-Rough 1/31/2025 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 1/31/2025 Corrections Issued DAVID ANDERSON
Sewer 1/31/2025 Corrections Issued DAVID ANDERSON
BUILDING-Rough-Frame 2/19/2025 Corrections Issued DAVID ANDERSON
ELECTRICAL-Rough 2/19/2025 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 2/19/2025 Partial Approval DAVID ANDERSON
Green Building Rough 2/19/2025 Not Ready for Inspection DAVID ANDERSON
Sewer 2/19/2025 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 2/19/2025 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 3/6/2025 Not Ready for Inspection DAVID ANDERSON
Deputy Wood Construction 6/17/2025 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 6/23/2025 Partial Approval DAVID ANDERSON
Gas Test 6/23/2025 Approved DAVID ANDERSON
Green Building Rough 6/23/2025 Approved DAVID ANDERSON
Rough-Elec/Plmb/HVAC 6/23/2025 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 6/23/2025 Partial Approval DAVID ANDERSON
Insulation 6/25/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 6/25/2025 Partial Approval DAVID ANDERSON
Deputy Wood Construction 7/8/2025 Conditional Approval DAVID MATSON
Shower Pan 7/15/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 7/23/2025 Approved WILLIAM WREN
Deputy Wood Construction 7/29/2025 Conditional Approval DAVID MATSON
Interior/Exterior Lathing 8/12/2025 Partial Approval DAVID ANDERSON
BUILDING-Rough-Frame 9/22/2025 Approved DAVID ANDERSON
Drywall Nailing 9/22/2025 Approved DAVID ANDERSON
Final 9/22/2025 Corrections Issued DAVID ANDERSON
Green Building Final 9/22/2025 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 9/22/2025 SGSOV Not Ready DAVID ANDERSON
Smoke Detectors 9/22/2025 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 9/22/2025 Approved DAVID ANDERSON
Final 10/1/2025 OK to Issue CofO DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 10/1/2025 SGSOV Approved DAVID ANDERSON