3218 W MADERA AVE 90039

Certificate Information: 3218 W MADERA AVE 90039

Application / Permit
23014-20000-03830
Plan Check / Job No.
B23VN12832
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
8'-2" X 5'-5" ADDITION TO AND CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK PER ENGINEERING.
Permit Issued
Issued on 10/18/2023
Issuing Office
Valley
Current Status
Issued on 10/18/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/20/2023 APPLICANT
Assigned to Plan Check Engineer 9/25/2023 ARTIN ZARUKIAN
Corrections Issued 9/26/2023 ARTIN ZARUKIAN
Building Plans Picked Up 9/27/2023 APPLICANT
Plan Check Approved 10/18/2023 ISIS ARGUETA
Issued 10/18/2023 APPLICANT

Permit Application Clearance Information

ZI Cleared 10/2/2023 DAVID URITA
Address approval Cleared 10/3/2023 DAVID VO
Roof/Waste drainage to street Cleared 10/3/2023 DAVID VO
Eng Process Fee Ord 176,300 Cleared 10/4/2023 JESSICA OPINION
Sewer availability Cleared 10/4/2023 JESSICA OPINION

Contact Information

Contractor Levelworks Construct & Renovate Inc; Lic. No.: 1044710-C53 5435 BALBOA BLVD UNIT 112      ENCINO, CA 91316
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/7/2023 Partial Inspection HAMIK HARTOUNIAN
Underground Mechanical 11/30/2023 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/13/2023 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 12/22/2023 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 1/16/2024 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/30/2024 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/30/2024 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 1/30/2024 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 2/13/2024 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/21/2024 Conditional Approval HAMIK HARTOUNIAN
Green Building Rough 2/21/2024 Approved HAMIK HARTOUNIAN
HVAC-Rough 2/21/2024 Approved HAMIK HARTOUNIAN
Insulation 2/29/2024 Approved RICHARD DOCKUS
Drywall Nailing 3/12/2024 Conditional Approval HAMIK HARTOUNIAN
Drywall Nailing 3/19/2024 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 4/9/2024 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/1/2024 Approved BRENDAN MORELLI
Final 7/1/2024 Corrections Issued BRENDAN MORELLI
Green Building Final 7/1/2024 Not Ready for Inspection BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 7/1/2024 SGSOV Not Required BRENDAN MORELLI
Smoke Detectors 7/1/2024 Approved BRENDAN MORELLI
Final 8/27/2024 Not Ready for Inspection THOMAS LOGRASSO
Final 10/25/2024 Not Ready for Inspection THOMAS LOGRASSO
Final 11/5/2024 Not Ready for Inspection THOMAS LOGRASSO