18818 W VALERIO ST 91335

Certificate Information: 18818 W VALERIO ST 91335

Application / Permit
23014-20000-03815
Plan Check / Job No.
B23VN12795
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
18'-8" X 37'-4" ADDITION TO (E) SFD. ALL WORK DONE PER WFPP. FIRE SPRINKLER REQUIRED THROUGHOUT.
Permit Issued
Issued on 10/12/2023
Issuing Office
Valley
Current Status
CofO Issued on 10/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2023 APPLICANT
Assigned to Plan Check Engineer 9/22/2023 ARTIN ZARUKIAN
Corrections Issued 9/23/2023 ARTIN ZARUKIAN
Building Plans Picked Up 9/25/2023 APPLICANT
Plan Check Approved 10/12/2023 MIROOSH KHACHATOORIAN
Issued 10/12/2023 APPLICANT
CofO in Progress 10/21/2024 JEFFREY BULL
CofO in Progress 11/20/2024 JOHN JANSON
No Progress 1/13/2025 SEAN WIRCH
Permit Finaled 10/2/2025 JOHN JANSON
CofO Issued 10/2/2025 JOHN JANSON
Permit Finaled 10/2/2025 JOHN JANSON

Permit Application Clearance Information

Low Impact Development (LID) Cleared 10/11/2023 LUIS LUVANO
Eng Process Fee Ord 176,300 Cleared 10/12/2023 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/12/2023 LEE GUILBEAUX
Sewer availability Cleared 10/12/2023 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 10/12/2023 LEE GUILBEAUX
Hold Cleared 11/15/2023 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/21/2023 Partial Approval JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Approved JEFFREY BULL
Green Building Rough 11/29/2023 Not Ready for Inspection JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Approved JEFFREY BULL
Green Building Rough 12/6/2023 Not Ready for Inspection JEFFREY BULL
PLUMBING-Rough 12/6/2023 Approved JEFFREY BULL
Special/Order Compliance 12/6/2023 Corrections Issued JEFFREY BULL
BUILDING-Rough-Frame 12/19/2023 Not Ready for Inspection JEFFREY BULL
Green Building Rough 12/19/2023 Not Ready for Inspection JEFFREY BULL
Rough-Elec/Plmb/HVAC 12/19/2023 Approved JEFFREY BULL
Verify Sprinkler Sign Off 12/19/2023 Not Ready for Inspection JEFFREY BULL
BUILDING-Rough-Frame 6/4/2024 Approved JEFFREY BULL
Drywall Nailing 6/4/2024 Approved JEFFREY BULL
Final 6/4/2024 Corrections Issued JEFFREY BULL
Footing/Foundation/Slab 6/4/2024 Approved JEFFREY BULL
Green Building Final 6/4/2024 Not Ready for Inspection JEFFREY BULL
Green Building Rough 6/4/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 6/4/2024 SGSOV Approved JEFFREY BULL
Smoke Detectors 6/4/2024 Not Ready for Inspection JEFFREY BULL
Final 9/20/2024 Not Ready for Inspection JEFFREY BULL
Green Building Final 9/20/2024 Approved JEFFREY BULL
Smoke Detectors 9/20/2024 Approved JEFFREY BULL
Final 10/21/2024 OK to Issue CofO JEFFREY BULL
Special/Order Compliance 11/21/2024 Corrections Issued ARUTYUN MADATYAN