22037 W PARTHENIA ST 91304
Certificate Information: 22037 W PARTHENIA ST 91304
- Application / Permit
- 23014-20000-03812
- Plan Check / Job No.
- B23VN12789
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 36'-0" X 16'-5" ADDITION TO (E) SINGLE FAMILY DWELLING FOR NEW FAMILY ROOM AND BATHROOM.
- Permit Issued
- Issued on 3/4/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 9/27/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 9/28/2023 | APPLICANT |
| Applicant returned to address corrections | 11/9/2023 | JESSE ARELLANO |
| Plan Check Approved | 12/1/2023 | GIOVANNY CHAVEZ |
| Issued | 3/4/2024 | APPLICANT |
| CofO in Progress | 11/6/2024 | CHRIS CHRISTENSEN |
| Permit Finaled | 11/8/2024 | JOHN JANSON |
| CofO Issued | 11/8/2024 | JOHN JANSON |
| Permit Finaled | 11/8/2024 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2023 | GABRIELLA TORRES |
| Roof/Waste drainage to street | Cleared | 10/30/2023 | GABRIELLA TORRES |
| Grading Pre-Inspection | Cleared | 11/6/2023 | ALEXANDER HELFER |
Contact Information
| Architect | Miller,, Michael; Lic. No.: C26956 | 12756 MITCHELL AVE LOS ANGELES, CA 90066 |
| Contractor | S K Home Designs And Remodeling; Lic. No.: 1026362-B | PO BOX 16700 ENCINO, CA 91416 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/19/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 3/19/2024 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2024 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 4/2/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2024 | Partial Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 6/18/2024 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 6/18/2024 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 6/18/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 6/26/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Shower Pan | 6/26/2024 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 7/9/2024 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 7/9/2024 | Approved | CHRIS CHRISTENSEN |
| Insulation | 7/9/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 7/9/2024 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 7/24/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 8/30/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 8/30/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 8/30/2024 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 8/30/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 11/5/2024 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 11/5/2024 | Approved | CHRIS CHRISTENSEN |