11124 W ARCHWOOD ST 91606
Certificate Information: 11124 W ARCHWOOD ST 91606
- Application / Permit
- 23014-20000-03796
- Plan Check / Job No.
- B23VN12747
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN 8'-3" X 9', 11'-3" X 13'-1" AND 5'-2" X 7'-3" ADDITIONS AND REMODEL TO (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/22/2024
- Issuing Office
- Current Status
- Issued on 5/22/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2023 | RAPHAEL ROSAS |
| Corrections Issued | 10/13/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 10/13/2023 | STEVEN KIM |
| Applicant returned to address corrections | 10/19/2023 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 12/19/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 1/8/2024 | RAPHAEL ROSAS |
| Issued | 5/22/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 10/24/2023 | COLIN LOREDO |
| Low Impact Development (LID) | Cleared | 11/22/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 11/25/2023 | BRYAN GODINEZ |
Contact Information
| Contractor | Grid Builders Llc; Lic. No.: 1058054-B | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/5/2024 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 6/12/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 6/29/2024 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 7/11/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 7/11/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/18/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 7/18/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Insulation | 7/18/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 9/10/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 9/10/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 9/10/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 9/17/2024 | Not Ready for Inspection | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2024 | Approved | JOSE AVILA |
| HVAC-Rough | 9/17/2024 | Conditional Approval | JOSE AVILA |
| PLUMBING-Rough | 9/17/2024 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 9/26/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 9/26/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 9/26/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 9/26/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Insulation | 10/4/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 10/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 10/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 10/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 10/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 10/15/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 10/15/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 10/28/2024 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 11/1/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 7/11/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 7/11/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 7/11/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 7/11/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 7/11/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/11/2025 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 7/11/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 7/28/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 7/28/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 7/28/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 7/28/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 7/28/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/28/2025 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 7/28/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 8/5/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 8/5/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/5/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 8/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 8/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 9/19/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 10/2/2025 | No Access for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 10/2/2025 | No Access for Inspection | ROBERTO PALACIOS-LOPEZ |