7826 N FAIR AVE 91352
Certificate Information: 7826 N FAIR AVE 91352
- Application / Permit
- 23014-20000-03779
- Plan Check / Job No.
- B23VN12694
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 40'-0" X 30'-0" DETACHED ACCESSORY DWELLING UNIT WITH 22'-10" X 9'-0" ATTACHED PATIO PER LAMC 12.22 A.33(c) and (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 5/24/2024
- Issuing Office
- Current Status
- CofO Issued on 3/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 9/23/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 9/25/2023 | APPLICANT |
| Applicant returned to address corrections | 3/14/2024 | GIOVANNY CHAVEZ |
| Issued | 5/24/2024 | APPLICANT |
| CofO in Progress | 2/28/2025 | MATTHEW NELSON |
| Permit Finaled | 3/11/2025 | RUBEN SALAS |
| CofO Issued | 3/11/2025 | RUBEN SALAS |
| Permit Finaled | 3/11/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/10/2023 | GABRIELLA TORRES |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2023 | GABRIELLA TORRES |
| Sewer availability | Cleared | 10/30/2023 | GABRIELLA TORRES |
| Low Impact Development (LID) | Cleared | 11/15/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 3/13/2024 | GABRIELLA TORRES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/16/2024 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2024 | Partial Approval | DAVID ANDERSON |
| PLUMBING-Rough | 8/13/2024 | Partial Approval | DAVID ANDERSON |
| Special/Order Compliance | 8/13/2024 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 8/15/2024 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2024 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2024 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 9/26/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 9/26/2024 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 9/26/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 10/18/2024 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 10/24/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 10/24/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 10/24/2024 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 10/24/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 11/1/2024 | Partial Approval | MATTHEW NELSON |
| Insulation | 11/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 11/7/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 11/18/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 11/25/2024 | Approved | MICHAEL CORTEZ |
| Sewer | 12/12/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 12/30/2024 | Partial Approval | MATTHEW NELSON |
| Final | 2/25/2025 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 2/25/2025 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 2/25/2025 | SGSOV Not Required | MATTHEW NELSON |
| Service/Power Release | 2/25/2025 | Corrections Issued | MATTHEW NELSON |
| Smoke Detectors | 2/25/2025 | Approved | MATTHEW NELSON |
| Final | 2/27/2025 | OK to Issue CofO | MATTHEW NELSON |
| Service/Power Release | 2/27/2025 | Approved | MATTHEW NELSON |