15824 W VALERIO ST 91406
Certificate Information: 15824 W VALERIO ST 91406
- Application / Permit
- 23014-20000-03777
- Plan Check / Job No.
- B23VN12690
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Convert (E) Detached Garage (372 S.F.) to a (N) ADU per LAMC 12.22 A.33 (c)-(d). All work per WFPP
- Permit Issued
- Issued on 4/8/2024
- Issuing Office
- Current Status
- CofO Issued on 2/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2023 | AMY GUEVARRA |
| Corrections Issued | 10/10/2023 | AMY GUEVARRA |
| Applicant returned to address corrections | 3/16/2024 | AMY GUEVARRA |
| Plan Check Approved | 3/25/2024 | AMY GUEVARRA |
| Issued | 4/8/2024 | APPLICANT |
| CofO in Progress | 2/6/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 2/19/2025 | RUBEN SALAS |
| CofO Issued | 2/19/2025 | RUBEN SALAS |
| Permit Finaled | 2/19/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/13/2023 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 10/13/2023 | COLIN LOREDO |
| ZA Case | Cleared | 10/16/2023 | YINGSHI HUANG |
| ZA Case | Cleared | 10/16/2023 | YINGSHI HUANG |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 11/15/2023 | COLIN LOREDO |
Contact Information
| Architect | Gemigniani,, Richard Louis; Lic. No.: NA18783 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/16/2024 | Approved | RAUL OLAGI |
| Sewer | 6/10/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 6/10/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Deputy Drilled-In Anchors | 6/11/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 6/12/2024 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 6/12/2024 | Partial Approval | RAUL OLAGI |
| Sewer | 6/12/2024 | Approved | RAUL OLAGI |
| Underground Mechanical | 6/12/2024 | Partial Approval | RAUL OLAGI |
| Underground Mechanical | 6/21/2024 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/19/2024 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 9/19/2024 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 9/19/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 9/19/2024 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 10/9/2024 | Partial Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 10/9/2024 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 10/9/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Rough | 10/9/2024 | Partial Approval | SALVADOR MARTINEZ |
| PLUMBING-Rough | 10/9/2024 | Approved | SALVADOR MARTINEZ |
| HVAC-Rough | 10/24/2024 | Approved | JENNIFER RABUCHIN |
| Insulation | 10/24/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/24/2024 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/14/2024 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 11/14/2024 | Approved | GAREN HAYRAPETYAN |
| Insulation | 11/14/2024 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 11/14/2024 | Approved | GAREN HAYRAPETYAN |
| Shower Pan | 11/14/2024 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 11/19/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 11/19/2024 | Approved | SALVADOR MARTINEZ |
| Special/Order Compliance | 12/9/2024 | Approved | SALVADOR MARTINEZ |
| Final | 1/16/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 1/16/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 1/16/2025 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Smoke Detectors | 1/16/2025 | Approved | SALVADOR MARTINEZ |
| Final | 2/6/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Green Building Final | 2/6/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 2/6/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Special/Order Compliance | 2/14/2025 | Corrections Issued | GAREN HAYRAPETYAN |