17546 W SEPTO ST 91325

Certificate Information: 17546 W SEPTO ST 91325

Application / Permit
23014-20000-03771
Plan Check / Job No.
B23VN12667
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 18'-1" x 19'-8" ADDITION TO THE (E) SINGLE FAMILY DWELLING FOR A NEW BEDROOM AND REMODEL.
Permit Issued
Issued on 10/26/2023
Issuing Office
Current Status
Issued on 10/26/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/18/2023 APPLICANT
Assigned to Plan Check Engineer 9/21/2023 ALEC MOUSAKHANIAN
Corrections Issued 9/22/2023 ALEC MOUSAKHANIAN
Applicant returned to address corrections 10/3/2023 KAMYAR EMAMI
Applicant returned to address corrections 10/10/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 10/13/2023 SARKIS HARABEDIAN
Plan Check Approved 10/25/2023 SARKIS HARABEDIAN
Issued 10/26/2023 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/27/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 9/29/2023 NIKKI ZULUETA
Sewer availability Cleared 9/30/2023 NIKKI ZULUETA

Contact Information

Contractor M D M Custom Remodeling Inc; Lic. No.: 930166-B       ,
Contractor Mdm General Contractor Room Additions; Lic. No.: 930166-B       ,
Engineer Medina,, Ferdinand Casaclang; Lic. No.: NA88007       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/7/2023 Conditional Approval MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 11/8/2023 Not Ready for Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 11/22/2023 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 12/15/2023 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 12/15/2023 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 12/15/2023 Approved JAVIER RAMOS JR
Green Building Rough 12/15/2023 Approved JAVIER RAMOS JR
HVAC-Rough 12/15/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 12/15/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 12/20/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 12/20/2023 Approved JAVIER RAMOS JR
Insulation 12/20/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 12/20/2023 Partial Approval JAVIER RAMOS JR
Drywall Nailing 12/26/2023 Approved JOHN COLEMAN
ELECTRICAL-Final 3/8/2024 Approved JAVIER RAMOS JR
Final 3/8/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 3/8/2024 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 3/8/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 3/8/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 3/8/2024 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 3/8/2024 Approved JAVIER RAMOS JR