6810 N YOLANDA AVE 91335

Certificate Information: 6810 N YOLANDA AVE 91335

Application / Permit
23014-20000-03768
Plan Check / Job No.
B23VN12657
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: SUPPLEMENTAL TO 23016-20000-21858 TO ADD A 8'-8" X 29'ADDITION TO REAR OF (E) SINGLE FAMILY DWELLING TO EXTEND (E) BEDROOM, ADD BATHROOM, AND ADD LAUNDRY ROOM. ALL WORK PER DESIGN.
Permit Issued
Issued on 10/4/2023
Issuing Office
Current Status
Permit Finaled on 1/7/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/18/2023 APPLICANT
Assigned to Plan Check Engineer 9/20/2023 OMAR GARNICA
Corrections Issued 9/21/2023 OMAR GARNICA
Plan Check Approved 10/4/2023 ALEC MOUSAKHANIAN
Issued 10/4/2023 APPLICANT
Permit Finaled 1/6/2025 ARUTYUN MADATYAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/2/2023 NIKKI ZULUETA
Roof/Waste drainage to street Cleared 10/2/2023 NIKKI ZULUETA

Contact Information

Architect Diradourian,, Richard C; Lic. No.: NA10336       ,
Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/30/2024 Partial Approval JEFFREY BULL
Deputy Drilled-In Anchors 9/4/2024 Approved JEFFREY BULL
Excavation/Setback/Form/Re-Bar 9/4/2024 Approved JEFFREY BULL
Footing/Foundation/Slab 9/4/2024 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 9/18/2024 Partial Approval JEFFREY BULL
ELECTRICAL-Rough 10/8/2024 Approved JEFFREY BULL
PLUMBING-Rough 10/8/2024 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Partial Approval JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 10/16/2024 Approved JEFFREY BULL
Drywall Nailing 10/21/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 11/7/2024 Partial Approval GEVORK IPCHYAN
Shower Pan 11/7/2024 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 12/20/2024 Not Ready for Inspection JEFFREY HARTLINE
Final 12/20/2024 Corrections Issued JEFFREY HARTLINE
Green Building Final 12/20/2024 Approved JEFFREY HARTLINE
Green Building Rough 12/20/2024 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 12/20/2024 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 12/20/2024 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 12/23/2024 Approved SEAN WIRCH
ELECTRICAL-Final 1/6/2025 Approved ARUTYUN MADATYAN
Final 1/6/2025 Permit Finaled ARUTYUN MADATYAN
PLUMBING-Final 1/6/2025 Approved ARUTYUN MADATYAN