2216 S GREENFIELD AVE 90064
Certificate Information: 2216 S GREENFIELD AVE 90064
- Application / Permit
- 23014-20000-03766
- Plan Check / Job No.
- B23VN12633
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE 10'-6"X 11'-4"PORTE-COCHERE. IRR. 24'X 21'ADDITION TO AND INTERIOR REMODEL TO THE (E) SFD. REMOVE FIREPLACE AND FILL-IN.
- Permit Issued
- Issued on 10/19/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2023 | ANGELICA DAVE |
| Corrections Issued | 9/18/2023 | ANGELICA DAVE |
| Plan Check Approved | 10/18/2023 | ISIS ARGUETA |
| Plan Check Approved | 10/18/2023 | ISIS ARGUETA |
| Issued | 10/19/2023 | APPLICANT |
| CofO in Progress | 10/8/2024 | DANIEL VERA |
| Permit Finaled | 10/15/2024 | RICHARD STEINBACH |
| CofO Issued | 10/15/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/15/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/6/2023 | MANUEL TEJADA |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2023 | BRENDEN HAWK |
| Roof/Waste drainage to street | Cleared | 10/17/2023 | BRENDEN HAWK |
Contact Information
| Contractor | Yaghoubi M Corp; Lic. No.: 972773-B | 6459 LUBAO AVENUE WOODLAND HILLS, CA 91367 |
| Engineer | Zolfaghari,, Saeed; Lic. No.: C86761 | 6201 BEE AVE AGOURA HILLS, CA 91301 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/3/2023 | Approved | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 11/3/2023 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Underground Mechanical | 11/22/2023 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 11/28/2023 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 11/30/2023 | Approved | KENNETH NAGLE |
| BUILDING-Rough-Frame | 12/5/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 12/5/2023 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 12/5/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 12/5/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2023 | Partial Approval | CARLOS MATAMOROS |
| HVAC-Rough | 12/7/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2023 | Corrections Issued | BEN MOLSTAD |
| Wood Frame | 12/8/2023 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 12/13/2023 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2023 | Approved | JESUS PINEDA |
| Green Building Rough | 12/13/2023 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Rough | 12/13/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 12/19/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Wood Frame | 12/19/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 12/26/2023 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 12/26/2023 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 12/26/2023 | Approved | MEL KHACHATOURIAN |
| Insulation | 1/5/2024 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 1/5/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 1/9/2024 | Approved | JESUS PINEDA |
| Final | 4/11/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 4/11/2024 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 4/11/2024 | SGSOV Not Ready | JESUS PINEDA |
| Smoke Detectors | 4/11/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 4/26/2024 | Approved | STEPHANIE SWANSON |
| Final | 4/26/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 4/26/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 4/26/2024 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 4/26/2024 | SGSOV Not Ready | STEPHANIE SWANSON |
| Final | 10/7/2024 | OK to Issue CofO | DANIEL VERA |
| Green Building Final | 10/7/2024 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 10/7/2024 | SGSOV Approved | DANIEL VERA |