6052-6054 N SADRING AVE 91367

Certificate Information: 6052-6054 N SADRING AVE 91367

Application / Permit
23014-20000-03764
Plan Check / Job No.
B23VN12625
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN Addition of 20' x 40' 3" two story ADU per LAMC 12.22 A.33 (c) and (e), and addition of attached one car garage. All work done per engineer.
Permit Issued
Issued on 11/28/2023
Issuing Office
Current Status
CofO in Progress on 1/2/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/20/2023 APPLICANT
Assigned to Plan Check Engineer 9/28/2023 NAREG ATARIAN
Corrections Issued 9/30/2023 NAREG ATARIAN
Quality Review Completed 10/4/2023 OMID HEDAYAT
Applicant returned to address corrections 10/31/2023 NAREG ATARIAN
Applicant returned to address corrections 11/8/2023 NAREG ATARIAN
Plan Check Approved 11/28/2023 NAREG ATARIAN
Issued 11/28/2023 APPLICANT
CofO in Progress 11/15/2024 TROY SANDERS
No Progress 1/2/2025 TROY SANDERS
CofO in Progress 1/2/2025 TROY SANDERS

Permit Application Clearance Information

Address approval Cleared 10/19/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/20/2023 COLIN LOREDO
Sewer availability Cleared 10/20/2023 COLIN LOREDO
Low Impact Development (LID) Cleared 10/25/2023 TRISH PARAS
Roof/Waste drainage to street Cleared 10/25/2023 COLIN LOREDO
Grading Pre-Inspection Cleared 10/31/2023 NAREG ATARIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Levin,, Vladimir; Lic. No.: C35001 11606 CHENAULT STR, UNIT 301      LOS ANGELES, CA 90049

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/18/2023 Approved TROY SANDERS
PLUMBING-Rough 1/4/2024 Partial Approval TROY SANDERS
Footing/Foundation/Slab 1/9/2024 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/19/2024 Partial Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/31/2024 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 2/23/2024 Approved TROY SANDERS
Deputy Wood Construction 2/23/2024 Approved TROY SANDERS
Green Building Rough 2/23/2024 Approved TROY SANDERS
Rough-Elec/Plmb/HVAC 2/23/2024 Approved TROY SANDERS
Insulation 3/4/2024 Approved TROY SANDERS
Interior/Exterior Lathing 3/4/2024 Partial Approval TROY SANDERS
Drywall Nailing 3/12/2024 Approved TROY SANDERS
Interior/Exterior Lathing 3/12/2024 Partial Approval TROY SANDERS
SGSOV-Seismic Gas S/O Valve 11/1/2024 SGSOV Not Ready TROY SANDERS
Final 11/5/2024 Corrections Issued TROY SANDERS
Green Building Final 11/5/2024 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 11/5/2024 SGSOV Approved TROY SANDERS
Smoke Detectors 11/5/2024 Approved TROY SANDERS
Final 11/14/2024 OK to Issue CofO TROY SANDERS
Special/Order Compliance 1/2/2025 Corrections Issued TROY SANDERS