20252 W GILMORE ST 91306
Certificate Information: 20252 W GILMORE ST 91306
- Application / Permit
- 23014-20000-03747
- Plan Check / Job No.
- B23VN12549
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. CONVERT (E) DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT. PER CGS 65852.2(e)(1)(A). STORAGE TO REMAIN
- Permit Issued
- Issued on 10/4/2023
- Issuing Office
- Current Status
- CofO Issued on 5/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2023 | NEHEMIAS RAMOS |
| Corrections Issued | 9/19/2023 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 9/27/2023 | NEHEMIAS RAMOS |
| Plan Check Approved | 9/29/2023 | RICARDO RAMIREZ |
| Issued | 10/4/2023 | APPLICANT |
| CofO in Progress | 4/24/2024 | ALEXANDER HANDY |
| Permit Finaled | 5/2/2024 | JOHN JANSON |
| CofO Issued | 5/2/2024 | JOHN JANSON |
| Permit Finaled | 5/2/2024 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 9/22/2023 | NELSON RODRIGUEZ |
| Address approval | Cleared | 9/23/2023 | COLIN LOREDO |
| Construction near power lines | Cleared | 9/23/2023 | WALTER RAMIREZ |
| Sewer availability | Cleared | 9/23/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/25/2023 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 11/28/2023 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2023 | Partial Approval | ALEXANDER HANDY |
| Wood Frame | 12/20/2023 | Partial Approval | ALEXANDER HANDY |
| Wood Frame | 1/5/2024 | Approved | ALEXANDER HANDY |
| Insulation | 1/11/2024 | Conditional Approval | ALEXANDER HANDY |
| Special/Order Compliance | 1/11/2024 | Corrections Issued | ALEXANDER HANDY |
| Drywall Nailing | 1/26/2024 | Approved | ALEXANDER HANDY |
| Pre-Inspection | 3/4/2024 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 3/29/2024 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Pre-Inspection | 4/5/2024 | Approved | ALEXANDER HANDY |
| Special/Order Compliance | 4/5/2024 | Approved | ALEXANDER HANDY |
| Final | 4/25/2024 | OK to Issue CofO | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 4/25/2024 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 4/25/2024 | Approved | ALEXANDER HANDY |