11055 W CALIFA ST 91601

Certificate Information: 11055 W CALIFA ST 91601

Application / Permit
23014-20000-03736
Plan Check / Job No.
B23VN12513
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE (E) 18'2" X 19'11" ATTACHED PATIO COVER FROM SFD. (N) 25'2" X 29'9" IRREGULARLY SHAPED ADDITION ( 447 SF) TO THE SFD. ALL WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 10/12/2023
Issuing Office
Current Status
CofO Issued on 5/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/14/2023 APPLICANT
Assigned to Plan Check Engineer 9/20/2023 SERGIO MUNIZ
Corrections Issued 9/20/2023 SERGIO MUNIZ
Building Plans Picked Up 10/2/2023 APPLICANT
Applicant returned to address corrections 10/10/2023 GIOVANNY CHAVEZ
Plan Check Approved 10/11/2023 MADISON ODELL
Issued 10/12/2023 APPLICANT
CofO in Progress 4/14/2024 JENNIFER RABUCHIN
Permit Finaled 5/1/2024 RUBEN SALAS
CofO Issued 5/1/2024 RUBEN SALAS
Permit Finaled 5/1/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/30/2023 CARLOS AGUILERA
Sewer availability Cleared 9/30/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/2/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/8/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 1/30/2024 Corrections Issued JOHN HAYES
Deputy Drilled-In Anchors 2/26/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 2/26/2024 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 2/28/2024 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 3/1/2024 Partial Approval JOHN HAYES
Special/Order Compliance 3/1/2024 Approved ROBERT GOLD
Deputy Drilled-In Anchors 3/6/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 3/12/2024 Approved JOHN HAYES
Deputy Drilled-In Anchors 3/15/2024 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 3/19/2024 Corrections Issued JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 3/19/2024 Partial Inspection JOHN COLEMAN
BUILDING-Rough-Frame 4/8/2024 Approved JENNIFER RABUCHIN
Deputy Wood Construction 4/8/2024 Approved JENNIFER RABUCHIN
Green Building Final 4/8/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 4/8/2024 Approved JENNIFER RABUCHIN
Insulation 4/8/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/8/2024 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 4/8/2024 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 4/12/2024 Approved JENNIFER RABUCHIN
Final 4/12/2024 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 4/12/2024 Approved JENNIFER RABUCHIN
HVAC-Final 4/12/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/12/2024 Approved JENNIFER RABUCHIN
Smoke Detectors 4/12/2024 Approved JENNIFER RABUCHIN